Upon receipt of the application and plans, the building inspector shall forward one set of plans to the planning commission for review and comment.
The planning commission shall review the application for compliance with the provision of this chapter and other applicable laws and regulations. The planning commission shall, within 30 days of receiving the application, make a written recommendation of approval, approval with conditions, or disapproval and forward to the building official.
The building official shall consider the recommendation of the planning commission and approve, approve with conditions or deny the application. If the application is approved, the applicant shall prepare and submit a binding site plan, which shall conform to the approval granted by the building official.
(Code 1966 § 17.16.040; Ord. 1281 § 1, 1998)