A.
Applicants for Type III and IV project permits are encouraged to participate in a preapplication conference with the director.
B.
The conference shall be held within 15 days of the request unless the applicant agrees to a longer time period. The preapplication conference will be scheduled by the director.
C.
The city shall provide the applicant with all available information pertinent to the project permit application process at the time of the preapplication conference and determine the applicable submittal requirements for the project as proposed. The discussion at the preapplication conference shall not bind or prohibit the city from future application or enforcement of all applicable law.
D.
The fee for a preapplication conference shall be as stated in the currently adopted fee schedule.
(Ord. 1227 § 19, 1996; Ord. 2133 § 3, 2024)