A.
A site development permit is required for all projects involving any of the following:
1.
Fill and/or excavation totaling 50 cubic yards or more. Note: Quantities of fill and excavation are separately calculated and then added together, even if excavated material is used as fill on the same site.
2.
Clearing 750 square feet or more, as measured at the ground level.
3.
Adding 120 square feet or more of new impervious surface.
4.
Retaining walls/rockeries over four feet in height as measured from the bottom of the base rock or block.
5.
Any grading or paving of an area used for a stormwater facility.
6.
Connection, extension and/or modification of the public and/or private storm and surface water drainage system(s) including, but not limited to, detention and other runoff control facilities.
B.
The town engineer shall specify the submittal and application materials which are required for a complete site development permit application.
C.
As a condition of applying for a site development permit, the applicant shall allow reasonable entrance by town staff to evaluate the project.
D.
A site development application must be submitted by the property owner, his/her agent, or his/her licensed and bonded contractor.
E.
Other Permits. It is the property owner's responsibility to identify and obtain all permits/approvals required for any proposed work.
F.
A Level 1 site development permit is required for a single-family residence which requires a new detention system, or changes to an existing detention system. All other site development permits shall be Level 2 permits.
(Ord. 607 § 1, 2009; Ord. 730 § 6, 2023)