The subdivider shall pay to the city the fees prescribed in this article for the activities and services listed. All fees shall be paid to the city treasurer.
(Res. 11-79 § VI, 7-24-1979)
(1) 
Tentative Maps (Four or Fewer Lots). For each tentative map, a fee of $250.00 plus $28.00 per lot plus pass through agreement.
(2) 
Tentative Subdivision Maps (Five or More Lots). For each tentative subdivision map, a fee of $496.00 plus $28.00 per lot plus pass through agreement.
(3) 
Final Maps. For each final map, a fee of $493.00 plus $28.00 per lot plus pass through agreement.
(4) 
Minor Division. For each minor division, a fee of $300.00.
(5) 
Lot Line Adjustment. For each lot line adjustment, a fee of $307.00.
(6) 
Certificate of Compliance. For each certificate of compliance, a fee of $200.00.
(7) 
Vesting Tentative Map. For each vesting tentative map, a fee of $596.00 plus $28.00 per lot plus pass through agreement.
(8) 
Plan Review. For each subdivision, a plan review fee equal to the actual cost to the city of the plan review required. The subdivider shall deposit with the city the estimated cost of the plan review as determined by the city engineer before work is started. Upon completion of the review and determination of actual cost, any excess deposit will be refunded by the city.
(9) 
Field Inspection. For each subdivision, a field inspection fee equal to the actual cost to the city of the inspection required. The subdivider shall deposit with the city the estimated cost of inspection, as determined by the city engineer, before work is started. Upon completion of work and determination of actual cost, any excess cost shall be paid by the subdivider or any excess deposit will be refunded by the city.
(Res. 11-79 § VI(A), 7-24-1979)
[1]
Code reviser's note: Fees shall be set in accordance with the latest fee schedule adopted by resolution by the Willows city council currently on file in the office of the city clerk.
Any owner or subdivider of a tract of land who desires the extension of sewer mains to serve their property shall make written application to the city manager. The application shall set forth the official number and/or legal description of the tract or subdivision, the total number and location of actual users and prospective users, and a map of the proposed development showing pertinent information.
Upon receipt of the application, the city engineer shall make a survey of the proposed extension and determine the estimated cost. Provided the application is approved by the city council, the owner or subdivider shall pay, in advance, the amount of estimated cost of the installation.
After completion of the installation and determination of the actual cost, any overpayment by the owner or subdivider will be refunded, or the unpaid balance of the cost shall be paid to the city.
(Res. 11-79 § VI(B), 7-24-1979)
A schedule of connection fees for each size sewer service shall be maintained in the office of the city clerk. Payment shall be made for each new sewer connection at the rate prescribed by said schedule for the size service requested.
(Res. 11-79 § VI(C), 7-24-1979)