(1)
Official filing of an application for subdivision with the director shall be preceded by a preliminary review of the proposed subdivision by the planning director and the town engineer.
(2)
Following the review, the subdivider shall submit an application to the planning director. A subdivider shall submit with the application 15 copies of a preliminary plat showing preliminary plans for streets and other improvements including but not limited to water lines, sewer lines, and drainage. Unless the subdivider requests otherwise, at the time of application the application will be processed simultaneously with applications for rezones of a planned unit development upon the property to be subdivided.
(3)
Applications shall be processed according to the procedures set forth in Chapter 19.68 CMC, Land Use Permit Process, and the additional procedures established in this article.
(4)
A preliminary plat shall be approved, disapproved or returned to the applicant for modification or correction within 90 days from date of filing unless the applicant consents to an extension of the time period. If an environmental impact statement is required as provided in RCW 43.21C.030, the 90-day period shall not include the time required for environmental review.
(Ord. 428 § 16.08.016, 1998)