[Amended 7-12-2018 by Ord. No. 2018-20]
A. Application submission and modifications. Written notification shall
be given by the Township, by e-mail or regular mail, to the Pinclands
Commission within seven days after a determination is made by the
Township that an application for development in the Pinelands Area
is complete or if a determination is made by the Township approval
agency that the application has been modified. Said notice shall contain:
(1) The name and address of the applicant.
(2) The legal description and street address, if any, of the parcel that
the applicant proposes to develop.
(3) A brief description of the proposed development, including uses and
intensity of uses proposed.
(4) The application number of the certificate of filing issued by the
Pinelands Commission and the date on which it was issued.
(5) The date on which the application or any change thereto was filed
and any application number or other identifying number assigned to
the application by the approval agency.
(6) The approval agency with which the application or change thereto
was filed.
(7)
The content of any change made to the application since it was
filed with the Commission, including a copy of any revised plans or
reports.
(8)
The nature of the municipal approval or approvals being sought.
B. Hearings. Where a meeting, hearing or other formal proceeding on
an application for development approval in the Pinelands Area is required,
the applicant shall provide notice to the Pinelands Commission by
e-mail, regular mail or delivery of the same to the principal office
of the Commission at least five days prior to such meeting, hearing
or other formal proceeding. Such notice shall contain at least the
following information:
(1) The name and address of the applicant.
(2) The application number of the certificate of filing issued by the
Pinelands Commission and the date on which it was issued.
(3) The date, time and location of the meeting, hearing or other formal
proceeding.
(4) The name of the approval agency or representative thereof that will
be conducting the meeting, hearing or other formal proceeding.
(5) Any written reports or comments received by the approval agency on
the application for development that have not been previously submitted
to the Commission.
(6) The purpose for which the meeting, hearing or other formal proceeding
is to be held.
C. Notice of approvals and denials. The Pinelands Commission shall be
notified of all approvals and denials of development in the Pinelands
Area, whether the approval occurs by action or inaction of any approval
agency or an appeal of any agency's decision. The applicant shall,
within five days of the approval or denial, give notice by e-mail
or regular mail to the Pinelands Commission. Such notice shall contain
the following information:
(1) The name and address of the applicant.
(2) The legal description and street address, if any, of the parcel that
the applicant proposes to develop.
(3) The application number of the certificate of filing issued by the
Pinelands Commission and the date on which it was issued.
(4) The date on which the approval or denial was issued by the approval
agency.
(5) Any written reports or comments received by the approval agency on
the application for development that have not been previously submitted
to the Commission.
(6) Any revisions to the application not previously submitted to the
Commission.
(7) A copy of the resolution, permit or other documentation of the approval
or denial. If the application was approved, a copy of any preliminary
or final plan, plot or similar document that was approved shall also
be submitted.
Where a prior approval has been granted by an
approval agency, no subsequent approval of an application for development
approval shall be obtained until one of the following is satisfied:
A. Notification is received from the Pinelands Commission
that review of the prior local approval is not required; or
B. Review of the prior local approval has been completed
pursuant to N.J.A.C. 7:50-4.37 through 4.42 and a final order regarding
the approval is received by the Township from the Pinelands Commission.
If the Pinelands Commission disapproves an application
for development previously approved by an approval agency, such approval
shall be revoked by the approval agency within 30 days and the agency
shall thereafter deny the application. If the Commission approves
the decision of an approval agency subject to conditions, the approval
agency which had previously approved the application shall, within
30 days, modify its approval to include all conditions imposed by
the Commission and, if final approval of the application is required,
shall grant final approval only if the application for approval demonstrates
that the conditions specified by the Commission have been met by the
applicant.
The Pinelands Commission may participate in
a hearing held in the Township involving the development of land in
the Pinelands Area pursuant to N.J.A.C. 7:50-4.36.
All development proposed by the Township or any agency thereof will comply with all the requirements for public development set forth in N.J.A.C. 7:50-4.51 et seq. and all the standards set forth in Articles
IV and
X of this chapter.
All applications for major development, forestry
and resource extraction shall be referred to the Environmental Commission
for review and comment.
In amending this chapter, Chapter
185, Flood Hazard Areas, Chapter
215, Land Use Procedures, Chapter
285, Site Plan Review, Chapter
297, Subdivision of Land, Chapter
313, Trees, Chapter
319, Vegetation, Obnoxious, Chapter
400, Sewage Disposal Systems, or any other chapter of this Code regulating the use of land or the Township's Master Plan, the Township shall comply with all the requirements of N.J.A.C. 7:50-3.45.