All water mains shall be no smaller than eight
inches in diameter. Written requests for exceptions shall be submitted
to the Town Engineer for approval. The Town Engineer may require the
installation of water mains of greater size than eight inches in diameter
if, in his judgment, service conditions so require.
All material and workmanship shall be subject
to inspection, examination and test by the Engineer or authorized
Town representative. The contractor shall submit manufacturer's certifications,
standards, fabrications and working drawings as required. Requests
for changes in types of materials and specification must be submitted
to the Town's Engineer in writing.
Plans and specifications by the contractor's
engineer must be submitted for approval. Prior to final acceptance,
one black and white transparency (ozalit) as-built drawing shall be
submitted to the Town Engineer. The contractor's engineer shall certify
that work has been installed under his supervision in conformance
with the plans and specifications.
Final inspection and acceptance of the facilities
by the Town shall occur within one year after completion of construction.
During the probationary period of one year, the contractor is to remedy
at his expense all defects in the work as may become evident or as
may be required by the Town Engineer.