A.
Immediately after backfilling and excavation, the public-service corporation shall place thereon an acceptable temporary resurfacing as hereinafter provided. Such temporary resurfacing shall be maintained even with the roadway or other surface, as directed, until permanent restoration of the surface is ordered by the Commissioner.
B.
The temporary resurfacing shall consist of not less than two inches of Amiesite or Colprovia or approved equal thereto when opening is made in an existing concrete, asphaltic bitulithic or macadam pavement, and not less than two inches of acceptable cinders in all other cases, except that where topsoil, seeded areas or sod have been disturbed by the excavation, the permittee shall restore the ground surface to the same condition as existed before the work began.
C.
Permanent restoration of the surface over a street opening excavation shall not be made until satisfactory settlement of the backfill has taken place, in the opinion of the Commissioner.