A.
All streets, storm sewers, sanitary sewers, water mains, curbs, sidewalks and other physical improvements to the property being subdivided or developed shall be provided, constructed and installed by the developer as shown on the approved final plan and all supplemental plans and drawings accompanying the preliminary plan and approved final plan. The developer shall execute a subdivision improvements agreement with the Township for the installation of all such improvements. All improvements shall be constructed in accordance with the applicable specifications of the Township or authority having jurisdiction or other applicable regulations. Where none apply, specifications of the Pennsylvania Department of Transportation and/or Pennsylvania Department of Environmental Protection shall be used. If none exist, specifications prepared by the Township Engineer shall be used.
B.
Supervision.
(1)
The installation of improvements required by § 154-32 following will be inspected by the Township as deemed necessary by the Township. The applicant shall reimburse the Township for the reasonable and necessary expense incurred for the observation of the improvements.
(2)
The developer's contractor shall schedule a meeting with the Township's representative prior to any construction. Construction drawings and specifications of all material to be used shall be submitted to the Township for approval prior to commencement of construction.
(3)
If the representative of the Township observing the construction or installation of improvements determines that the work is not in accordance with approved plans and specifications or is not being done in a workmanlike manner, said representative may stop work and/or require corrections to be made. Prior to any construction or installation, a forty-eight-hour start work notice is to be given to the Township representative who will observe the construction.