[HISTORY: Adopted by the Town Meeting of the Town of Killingworth 8-21-1989. Amendments noted where applicable.]
The purpose of this chapter is to regulate all underground storage tanks that hold fuel oil and chemicals and which are currently excluded from regulations of the State Department of Environmental Protection.
As used in this chapter, the following terms shall have the meaning indicated:
FUEL OIL
Oil or petroleum-based liquids used for heating purposes.
HAZARDOUS MATERIALS
Any material defined by federal regulations, 40 CFR, Part 261, Subpart C, generally, having the characteristics of one or more of the following: ignitibility, corrosivity, reactivity or toxicity, but not including a hazardous waste currently regulated by the Connecticut Department of Environmental Protection.
LISTED
Approved by the Commissioner of Environmental Protection, in accordance with § 22a-449(d)-1 of the Regulations of Connecticut State Agencies.
NONRESIDENTIAL FUEL OIL STORAGE
Underground storage of less than 2,100 gallons of fuel oil at nonresidential locations.
PIPING
Any pipe intended to regularly hold or convey fuel oil or hazardous materials.
RESIDENTIAL FUEL OIL STORAGE
Underground storage of fuel oil at any residential building, regardless of volume stored.
UNDERGROUND
Any facility or component of a facility that has 10% or more of its capacity below the surface of the ground and not readily visible for inspection.
UNDERGROUND TANKS
All underground containers used for residential fuel oil storage and nonresidential fuel oil storage as well as those for storing hazardous materials.
Owners of all existing underground tanks shall register these tanks with the Town Sanitarian or designated agent on forms provided by the Sanitarian or designated agent. Information to be provided shall include but not be limited to address of tank location; approximate location of tank in relation to nearby building(s); approximate date of installation; type of material tank consists of and approximate volume; diameter and length of all buried piping; copy of manufacturer's warranty, if available; type of material tank contains; and such other information as may be required. This registration shall be completed within nine months after the effective date of this chapter.
No underground tank shall be installed at any facility, such as a home or business, after the effective date of this chapter unless the installation complies with the following requirements:
A. 
Permit. A permit to install an underground tank must be completed by the applicant and approved by the Town Sanitarian or designated agent prior to the initiation of any work. Such permit shall contain the tank's street address, location on the property, and the type of tank, as well as other information deemed appropriate by the Town Sanitarian or designated agent.
B. 
Tank type. All new underground tanks must be a listed, double-walled steel or single-walled fiberglass-reinforced plastic tank. Steel tanks must be cathodically protected for a minimum of 30 years and equipped with permanent cathodic protection monitoring devices and be externally coated with a factory-applied coating designed to retard corrosion in underground locations. Fiberglass-reinforced plastic tanks must be chemically compatible with the material to be contained, as determined by the tank manufacturer.
C. 
Installation. Installation of underground tanks and all related components shall conform to NFPA 30, as amended, and the manufacturer's installation specifications, whichever imposes the most stringent requirements. Within 30 days after completion of installation, but prior to use of the tank, the owner of the tank must submit a statement to the Town Sanitarian or designated agent, signed by the tank installer, certifying that the installation has been carried out in accordance with the provisions of this section.
D. 
Piping. All piping must be installed by a plumber licensed in the state and shall be sleaved in at least four-inch diameter Schedule 40 plastic conduit meeting the requirements of ASTM D-1785, or equivalent, with appropriate tight joints. This sleeving shall be provided at all points where the supply or return piping is underground, as well as through the foundation wall, and if this piping is to be buried in or below a concrete floor. All piping and the tank shall hold an air pressure of five pounds per square inch gauge (psig) for at least 10 minutes after backfilling but prior to use. A statement certifying the successful completion of this air test must be signed by the plumber and submitted to the Town Sanitarian or designated agent within 30 days of such test but prior to use of such piping.
E. 
Inspection. As further assurance that installations are performed in accordance with applicable requirements, as detailed above, an inspection of all installations must be made by the Town Sanitarian or designated agent. Such official must be notified at least 24 hours prior to such an installation.
The life expectancy of all fiberglass-reinforced plastic underground tanks installed after the effective date of this chapter shall be that indicated in the manufacturer's corrosion warranty. The life expectancy for all cathodically-protected underground tanks installed after the effective date of this chapter shall be that indicated in the tank manufacturer's corrosion warranty.
A. 
Extended life expectancy. This life expectancy can be extended for up to five additional years beyond this life expectancy if no leaks have been detected previously and no leaks are detected in this extended life expectancy, as detailed in § 425-6.
B. 
Leaks. If the underground tank or piping is determined to have a leak at any time, use of the tank shall be immediately discontinued, the tank shall be emptied and the Town Sanitarian or designated agent notified within two business days. The Town Sanitarian or designated agent, in consultation with the Department of Environmental Protection, shall have the right to require that reasonable efforts be taken to recover lost products and remove and properly dispose of contaminated materials, such as soil. If only the piping is leaking, it may be replaced or repaired, as necessary, in general conformance with the requirements for piping in § 428-4, New installations. If the underground tank leaks before the life expectancy has been reached, or in the extended life expectancy, it shall be substantially emptied and removed or abandoned in accordance with NFPA 30. This removal or abandonment must be done within 90 days of the detection of a leak.
C. 
Abandonment/removal. After the life expectancy, or the extended life expectancy, has been reached, the tank shall be substantially emptied and removed or abandoned in accordance with NFPA 30. This removal or abandonment must be achieved within six months after reaching the life expectancy or extended life expectancy, whichever is applicable.
Upon the effective date of this chapter, all underground tanks shall be monitored by the tank owner for excessive, unanticipated product loss on a regular basis. This monitoring shall consist of the following minimum procedures or an equivalent method approved by the Town Sanitarian or designated agent. Records shall be kept of average product use per degree-day for each heating fuel tank. If this ratio shows an increase or decrease of greater than 10% in any single monitoring period, further investigation shall be initiated to determine the cause. Such further investigation may include but not be limited to review of product use at location of underground tank, visual inspection of tank components, or the use of more sophisticated leak detection methods.
A. 
If this further investigation fails to identify the cause of the product loss, the Town Sanitarian or designated agent shall be notified within two business days. The Town Sanitarian or designated agent shall exercise general oversight in the determination and investigation of any apparent leaks at this stage. The Sanitarian or designated agent shall have the right to require precision hydrostatic testing and/or partial or entire excavation of the tank and related components, if necessary.
B. 
The monitoring records and any supporting documentation of product use shall be submitted to the Town Sanitarian or designated agent upon request.
Any person aggrieved by a decision of the Town Sanitarian or designated agent in relation to the provisions of this chapter may appeal to the Water Pollution Control Authority. The Authority shall schedule a public hearing, after proper notice, to investigate into the facts and may vacate, modify or affirm the decision of the Town Sanitarian or designated agent. Any such action by the Water Pollution Control Authority shall be recorded on the permit and/or registration form for such underground tank.
[Amended 6-11-2008]
Any person who violates any provision of this chapter shall be subject to a fine of not more than $250 per day, or portion thereof, during which a violation is maintained.