A.Â
Permit requirements. Approval of a road construction
plan is required. A grading or building permit may not be issued for
any parcel or lot unless the road construction plan and supporting
materials have been approved by the Department as meeting all the
requirements of this Part 3 and is in conformance with the Roads Design
Manual.
B.Â
Other requirements. A grading permit for new road
construction may not be issued without:
(1)Â
All revisions to the road construction plan being
made and duly noted;
(2)Â
An approved surety for the construction;
(3)Â
A paid inspection fee;
(4)Â
Preparation and execution of a right-of-way deed granting
the County the road right-of-way in fee simple;
(5)Â
Documented permission from adjacent property owners
as necessary;
(6)Â
Submission and approval of the construction sequence
schedule;
(7)Â
Issuance of all utility permits to each respective
utility company;
(8)Â
Issuance of any other permits from all County, state
and federal agencies necessary for any phase of construction to the
developer; and
(9)Â
Holding a preconstruction meeting between the developer,
the Department, any state and federal agencies affected by the project,
and a representative from each utility company that will be providing
services to the development.
C.Â
Form of permit. The construction permit shall be in
the form of a signed road construction plan.
Any grading or building permit issued by the
Department may be suspended or revoked after written notice is given
to the permittee for any of the following reasons: