A. 
A developer shall perform all aspects of road construction required by this Part 3 and in accordance with the Roads Design Manual.
B. 
Installation of utilities. The developer shall install all applicable utilities, including electric, telephone, cable TV and central gas lines, so as to minimize conflicts with the roadway structure and public water and sewer lines and shall:
(1) 
Apply for and follow all conditions enumerated in the utilities permit as issued by the Department.
(2) 
Install all components of utilities, including trunk lines, mains and service connections, in conjunction with the appropriate phase of roadway construction so as to minimize any conflicts;
(3) 
Install the utilities in a designated utility easement as shown on the road plan;
(4) 
Coordinate the installation of utilities with the Department; and
(5) 
Comply with all other local, state, or federal requirements respecting the installation and provision of utilities.
The Department may require a developer to improve or upgrade an existing County road when a development occurs to ensure that:
A. 
Consistent planning, design and construction standards are met;
B. 
The road is suitable for the nature of the traffic proposed by the development; and
C. 
All public safety concerns are addressed. The nature of the improvements or upgrades may include but are not limited to resurfacing, installation of traffic control devices or lighting, intersection realignments, right-of-way dedication, road widening, sidewalks or pedestrian paths, entrance or access improvements and drainage improvements.