A.
The City Engineer has prepared an enforcement response plan. The enforcement response plan, in a step-by-step fashion, outlines the procedures to be followed to identify, document and respond to violations by users of the POTW. All violations by users of the POTW shall be met with some type of enforcement response. The response shall be comprehensive and effective.
B.
The enforcement response plan:
(1)
Describes how the City Engineer will investigate instances of noncompliance.
(2)
Describes the types of escalated enforcement actions that the City Engineer will take in response to all anticipated types of user violations and the time periods within which to initiate and follow up these actions.
(3)
Reflects the City Common Council's responsibility to enforce all applicable standards and requirements.
C.
The enforcement response plan contains:
(1)
Criteria for scheduling periodic inspection and/or sampling visits to POTW users.
(2)
Forms and guidelines for documenting compliance data in a manner which will enable the information to be used as evidence.
(3)
Systems to track due dates, compliance schedule milestones and pending enforcement actions.
(4)
Criteria, responsible personnel and procedures to select and initiate an enforcement action.
D.
The range of appropriate enforcement actions shall be based on the nature and severity of the violation and other relevant factors, such as:
(1)
Magnitude of the violation;
(2)
Duration of the violation;
(3)
Effect of the violation on the receiving water;
(4)
Effect of the violation of the POTW;
(5)
Effect of the violation of the health and safety of the POTW employees;
(6)
Compliance history of the user;
(7)
Good faith of the user, as shall promote consistent and timely use of enforcement remedies.
E.
The City Common Council has adopted the enforcement response plan. The enforcement response plan, which is incorporated by reference herein, shall be and is hereby deemed to be a part of this Part 2. A copy of the adopted enforcement response plan may be obtained from the City Engineer. The enforcement response plan shall be reviewed about every five years.