EXAMPLE: A twelve-foot-by-twenty-foot shed is 240 square feet;
240 square feet x $25 per square foot = $6,000 (which is the estimated
cost), then fees are calculated by the estimated cost.
$6,000 x $16.26 = $97.56 + $20 zoning fee + $5 certificate of
compliance = TOTAL FEE DUE: $122.56.
All calculations are done by the Building Department.
**NOTE: This is only an example to understand the fee structure.
| ||
---|---|---|
Item
|
Estimated Cost Calculated by the Following
(per square foot)
| |
Basement unfinished
|
Included with new house/addition
| |
Basement finished
|
$37
| |
Living space
|
$80
| |
Garage unfinished
|
$45
| |
Garage finished
|
$50
| |
Shed
|
$25
| |
Deck
|
$20
| |
Covered porch
|
$35
| |
Storage (unfinished areas convertible to living
space)
|
$40
|