A.
Sewers shall be designed for capacity and flow in accordance with the Recommended Standards for Sewage Works (Ten State Standards).
B.
No gravity sewer conveying raw sewage shall be less than eight inches in diameter.
C.
Sewers shall be laid true to line and grade with a uniform slope between manholes. Sewers 24 inches or less shall be laid with straight alignment between manholes.
D.
Manholes shall be installed at the end of each line; at all changes in grade, size or alignment, at all pipe intersections; and at distances not greater than 300 feet. A drop manhole, with an exterior drop pipe, shall be constructed for a sewer entering a manhole at an elevation of 24 inches or more above the manhole invert.
E.
Sewers shall be laid at least 10 feet horizontally from any existing or proposed water main. The distance shall be measured edge to edge. Sewers crossing water mains shall be laid to provide a minimum vertical distance of 18 inches between the outside of the water main and the outside of the sewer. The crossing shall be arranged so that the sewer pipe joints will be equidistant and as far as possible from the water main joints. Any deviation from the minimum horizontal and vertical separation distances must be specifically approved by the Orange County Department of Health.
F.
Prior to beginning the installation of sewers, the developer shall submit to the Commissioner of Public Works or his duly authorized representative the following items for review and approval: