All required subdivision improvements shall be subject to inspections by the Town Engineer or his authorized representative.
A.
Construction schedule.
(1)
The developer shall supply the Planning Board with a schedule of construction showing the beginning and completion dates of each of the following phases of construction:
B.
Notification.
(1)
The developer shall notify the Planning Board in writing five days prior to the completion of each construction phase listed above.
C.
Testing.
(1)
The following tests shall be approved by the Town Engineer at the applicant's expense:
(a)
Subbase. One sample per 1,000 feet with a minimum of two samples per road. This minimum will be supplemented by additional sampling if variations in the types of soil are detected by the technicians. These samples will be tested in the laboratory in accordance with § 220-3.23.
(b)
Stabilized base. Generally one design per subdivision will be made unless the soil varies so much that one design is not practical or that one of the materials used as a stabilizer is changed. This design shall be submitted for approval prior to construction of the base. (See § 220-3.23C.)
(c)
Asphaltic concrete paving. One core from the finished pavement will be taken for each 1,000 feet of road or if the road is less than 1,000 feet, one core per road. There shall be a minimum of two cores per project, with the project area submitted to the Town Engineer for acceptance. The cores will be returned to the laboratory and tested for the following:
(2)
The Town Engineer will make the required field inspections and, depending on the results of these inspections, additional tests may be required.