No building in any district shall be erected, reconstructed, repaired, restored or structurally altered without a building permit duly authorized upon application to the Building Inspector, nor shall any such building be demolished without a demolition permit similarly issued. No building permit or demolition permit shall be issued unless the proposed construction or use is in full conformity with all of the provisions of this chapter. Any building permit issued in violation of the provisions of this chapter shall be null and void and of no effect without the necessity for any proceedings for revocation or nullification thereof, and any work undertaken or use established pursuant to any such permit shall be unlawful. The provisions of Chapter 59, Building Construction, are hereby referenced where applicable.
A.
Every application for a building permit shall contain the following information and be accompanied by the required fee and by a plot plan drawn to scale and signed by the person responsible for preparing such drawing. If no such plot plan is available, a survey prepared by a licensed engineer or land surveyor is required.
(1)
The actual shape, dimensions, radii, angles and area of the lot on which the building is proposed to be erected, or of the lot on which it is situated, if an existing building.
(2)
The section, plate, block and lot numbers as they appear on the latest tax records.
(3)
The exact size and location on the lot of the proposed building or buildings or alteration of an existing building and of other existing buildings on the same lot.
(4)
The dimensions of all yards in relation to the subject building and the distances between such building and any other existing buildings on the same lot.
(5)
The existing and intended use of all buildings, existing or proposed; and the use of land and the number of dwelling units the building is designed to accommodate.
(6)
Such topographic or other information with regard to the building, the lot or neighboring lots as may be necessary to determine that the proposed construction will conform to the provisions of this chapter.
B.
No building permit shall be issued for the construction or alteration of any building upon a lot without access to a street or highway, as stipulated in § 280-a of the Town Law.
C.
No building permit shall be issued for any building where the site plan for such building is subject to approval by the Planning Board, except in conformity with the plans approved by said Board.
D.
No building permit shall be issued for a building to be used for any special permit use in any district where such use is subject to approval by the Town Board, unless and until such approval has been duly granted by the Town Board and site plan approval has been duly granted by the Planning Board, as required in this chapter.[1]
[1]
Editor's Note: Former § 85-29(5), regarding building permits, which immediately followed this section, was deleted 4-13-1999 by L.L. No. 1-1999.
E.
The Building Inspector shall, within 10 days after the filing of a complete and properly prepared application, either issue or deny a building permit. If a building permit is denied, the Building Inspector shall state, in writing, to the applicant the reasons for such denial.
F.
Every building permit shall expire if the work authorized has not commenced within 12 months after the date of issuance or has not been completed within 18 months from such date for construction costing less than $1,000,000 and has not been completed within 30 months from such date for construction costing in excess of that amount. If no zoning amendments or other codes or regulations affecting the subject property or use have been enacted in the interim, the Building Inspector may authorize, in writing, the extension of either of the above periods for an additional six months, following which no further work is to be undertaken without a new building permit.
G.
As soon as the foundation of a building or any addition to an existing building is completed and before first story framing or wall construction is begun, there shall be filed with the Building Inspector an accurate survey, signed by the person responsible for said survey, showing the exact location of such foundation with respect to the street and property lines of the lot.
I.
Dwelling relocation.
[Added 6-30-2004 by L.L. No. 2-2004]
(1)
No building permit shall be issued for a dwelling relocation in an approved subdivision unless the following requirements are met:
(a)
The relocated dwelling remains on 80% of the area of the originally approved dwelling location.
[Amended 3-6-2006 by L.L. No. 2-2006]
(b)
The relocated house is within required setback lines.
(c)
The well shall not be relocated and the sewage disposal system shall not be relocated off the area where approved percolation tests were recorded. If the project was approved by the Orange County Department of Health, relocation of wells and sewage disposal systems are subject to all terms and conditions of such approval, including the prohibition of any such relocation, if so stated.
(d)
The driveway meets maximum grade requirements.
(e)
The sewage from the dwelling will discharge by gravity to the sewage disposal field unless a lift or pump station has already been approved for the lot.
(f)
Drainage patterns on the lot may not be changed so as to adversely impact adjacent properties.
(g)
Driveway curb cut or lot access may not be relocated.
(h)
House location shall not be shifted onto an environmentally sensitive site feature such as a federal or state wetland or buffer.
(i)
House location shall not be shifted into a previously approved agricultural buffer.
(j)
House shall not be shifted in a location which is otherwise in contravention of a requirement of the subdivision regulations, zoning law, as may be amended, or of the findings or determination under the SEQRA for the subdivision for which the house lot is a part.
(2)
If all requirements are not met, the matter must be referred back to the Planning Board for further review.