A.
B.
Major subdivision.
(1)
The subdivider submits the preliminary plat, together with the fee and supporting material, including topographic map and road and drainage profiles, to the Office of the Planning Board.
(2)
The Planning Board holds a public hearing, as required by law, on the preliminary plat.
(3)
The Planning Board either approves, with or without modification, or disapproves the preliminary plat.
(4)
The subdivider submits the final plat, together with supporting material, to the Office of the Planning Board.
(5)
The Planning Board may hold a public hearing or waive such public hearing on the final plat if it is deemed to be in substantial agreement with approved preliminary plat.
(6)
The Planning Board may either conditionally approve, with or without modifications, disapprove or grant final approval and authorize the signing of the final plat.
(7)
The Planning Board advises the subdivider of required public improvements, park dedication provisions and bond amount.
(8)
The subdivider posts a performance bond guaranty of the installation of required public improvements or furnishes proof of the satisfactory completion of the same.
(9)
The subdivider pays the inspection fee, and in cases where the Planning Board finds that it is in the best interest of the municipality to waive the dedication of land for park purposes, pays the park fee.
(10)
The Planning Board Chairman or Vice Chairman signs final plat.
(11)
The subdivider files the final plat in the office of the County Clerk.
(12)
The Building Inspector issues building permits upon proper application by the subdivider.
(13)
The subdivider constructs required public improvements under inspection of the Municipal Engineer.
(14)
The subdivider requests release of bond after completion of required public improvements, and the subdivider shall post a maintenance bond.
(15)
The Planning Board may permit the subdivider to install the required improvements without posting a bond. In that case, the procedure is the same as that outlined above, except that no building permit will be issued until completion of such improvements and:
(a)
Instead of posting a performance bond, a subdivider installs required public improvements within a period of time established by the Planning Board, subject to the same inspection fee and procedure as that set forth for public improvements under the performance bond procedure, and the subdivider will be required to obtain an excavation and regrading permit and post a restoration bond.
(b)
Before the Chairman or Vice Chairman signs the final plat, the subdivider must complete all improvements to the satisfaction of the Municipal Engineer.