Prior to the granting of final approval, the subdivider shall have installed or furnished performance guarantees as set forth in Article
VIII for the ultimate installation of the improvements described below. All improvements shall be subject to approval and inspection by the Township Engineer, who shall be notified by the developer at least two weeks prior to the start of construction of any improvements. No underground installation shall be covered until inspected and approved.
A. Compliance required. The developer shall observe the
requirements and principles of land subdivision and site design of
each development or portion thereof, as set forth in this article.
B. General standards. The development shall conform to
design standards that will encourage good development patterns within
the Township. The development shall conform to the proposals and conditions
shown on the Official Map, if there be one, and Master Plan of the
Township. The streets, drainage or other areas shown on the officially
adopted Master Plan or Official Map shall be considered in approval
of all developments.
Prior to the granting of final approval, the applicant shall have installed or furnished performance guaranties as set forth in Article
VIII for the ultimate installation of any required public on-tract improvements as the same are described in §
102-49. In addition, the Planning Board may require the installation of on-site improvements, as described in §
102-51 below, prior to the granting of final approval and which it finds essential before the issuance of a building permit. All such improvements shall be subject to approval and inspection of the Township Engineer.