A.
These specifications contain the design and construction requirements of the Town of Boston for roads, ditches and appurtenant structures. Circumstances and conditions which are not covered by these specifications will be submitted to the Town Highway Superintendent for consideration and decision.
B.
Construction permit.
(1)
Construction work shall not be started without a construction permit. In the case of a subdivision, said permit will not be issued until the subdivision map has received final review of the Planning Board. The final approval of the subdivision map, by the Planning Board, shall be made after the completion of construction of the roads, ditches and appurtenances and the recommendation of the acceptance of the same by the Highway Superintendent.
(2)
Application for a construction permit shall be made to the Town of Boston Highway Superintendent accompanied by two complete sets of design plans and specifications. Plans and specifications will be reviewed by the Highway Superintendent and the Town Engineer. Permits will be issued by the Town Board upon receipt of favorable recommendation from the Highway Superintendent and the Town Engineer upon payment of a fee to be established by the Town Board. All construction work which is done without the required permit and which is in conflict with the requirements of the Town Board or is not in conformance with approved plans and specifications shall be removed or changed to meet these requirements at the expense of the owner.
C.
The owner must also submit a time schedule for the work in accordance with the requirements of these specifications.