A.
With submittal of the application for final plan approval, the applicant shall provide one of the following performance guarantees for an amount adequate to cover the total construction costs of all required improvements, taking into account the time span of the construction schedule and the inflation rate for construction costs:
(1)
Either a certified check payable to the municipality or a savings account or certificate of deposit for the establishment of an escrow account in such form as permitted by law and approved as to form by the Town Attorney;
(2)
An irrevocable letter of credit from a financial institution establishing funding for the construction of the subdivision, from which the Town may draw if construction is inadequate, approved by the Town Council or Town Attorney; or
B.
The conditions and amount of the performance guarantee shall be determined by the Planning Board with the advice of the Town Engineer, Public Works Director, Town Council, and/or Town Attorney.