In his written certification as required above, the developer's professional
engineer or qualified licensed land surveyor shall state clearly that he or
his authorized representative has inspected all phases of the street construction
and that all work has been completed in accordance with the approved plans
and specifications.
Sanitary sewer and water lines, as required, and all storm drainage
work shall be installed in accordance with plans and specifications acceptable
to the Village Engineer. Not later than three days prior to the time any utility
work is proposed to be covered up, the subdivider shall notify the Village
Engineer that the work is ready for his inspection. No utility lines shall
be covered without having been inspected and certified as acceptable by the
Village Engineer.