A. 
At least five days prior to commencing each major phase of construction of required improvements, the subdivider or builder shall notify the Code Enforcement Officer, in writing, of the time when he proposes to commence construction of such improvements, so that the municipal officers can cause inspection to be made to assure that all municipal specifications and requirements shall be met during the construction of required improvements and to assure the satisfactory completion of improvements and utilities required by the Board.
B. 
If the inspecting official finds upon inspection of the improvements that any of the required improvements have not been constructed in accordance with the plans and specifications filed by the subdivider, he shall so report, in writing, to the municipal officers, Planning Board and the subdivider or builder. The municipal officers shall take any steps necessary to preserve the municipality's rights.
C. 
If at any time before or during the construction of the required improvements, it appears to be necessary or desirable to modify the required improvements, the inspecting official is authorized to approve minor modifications due to unforeseen circumstances, such as encountering hidden outcrops of bedrock, natural springs, etc. The inspecting official shall issue any approval under this section in writing and shall transmit a copy of the approval to the Board. Revised plans shall be filed with the Town. For major modifications, such as relocation of rights-of-way, property boundaries, changes of grade by more than 1%, etc., the subdivider shall obtain permission to modify the plans from the Board.
D. 
At the close of each summer construction season, the Town shall, at the expense of the subdivider, have the site inspected by a qualified individual. By December 1 of each year during which construction was done on the site, the inspector shall submit a report to the Board based on that inspection, addressing whether stormwater and erosion control measures (both temporary and permanent) are in place, are properly installed and appear adequate to do the job they were designed for. The report shall also include a discussion and recommendations on any problems which were encountered.
E. 
Prior to the sale of any lot, the subdivider shall provide the Board with a letter from a registered land surveyor, stating that all monumentation shown on the plan has been installed.
F. 
Upon completion of street construction and prior to a vote by the municipal officers to submit a proposed Town way to a Town meeting, a written certification signed by a professional engineer registered in the State of Maine shall be submitted to the municipal officers at the expense of the applicant, certifying that the proposed Town way meets or exceeds the design and construction requirements of these regulations. If there are any underground utilities, the servicing utility shall certify, in writing, that they have been installed in a manner acceptable to the utility.
G. 
The subdivider or builder shall be required to maintain all improvements and provide for snow removal on streets and sidewalks until acceptance of the improvements by the municipality.
A. 
No plan of a division of land within the municipality which would constitute a subdivision shall be recorded in the Registry of Deeds until a final plan has been approved by the Board in accordance with these regulations.
B. 
No person, firm, corporation or other legal entity may convey, offer or agree to convey any land in a subdivision which has not been approved by the Board and recorded in the Registry of Deeds.
C. 
No person, firm, corporation or other legal entity may convey, offer or agree to convey any land in an approved subdivision which is not shown on the final plan as a separate lot.
D. 
Any person, firm, corporation or other legal entity who conveys, offers or agrees to convey any land in a subdivision which has not been approved as required by these regulations shall be punished by a fine of not less than $100 and not more than $2,500 for each such conveyance, offering or agreement. The. municipality may institute proceedings to enjoin the violation of these regulations, and may collect attorneys' fees and court costs if it is the prevailing party.
E. 
No public utility, water district, sanitary district or any utility company of any kind shall serve any lot in a subdivision for which a final plan has not been approved by the Board.
F. 
Development of a subdivision without Board approval shall be a violation of law. Development includes grading or construction of roads, grading of land or lots or construction of buildings which require a final plan approved as provided in these regulations and recorded in the Registry of Deeds.
G. 
No lot in a subdivision may be sold, leased or otherwise conveyed before the street upon which the lot fronts is completed in accordance with these regulations up to and including the entire frontage of the lot. No unit in a multifamily development shall be occupied before the street upon which the unit is accessed is completed in accordance with these regulations.