Description
|
Fee
| ||
---|---|---|---|
Advisory opinion from Planning Board's Administrative
Officer
|
$100
| ||
Advisory opinion before Planning Board
|
$150
| ||
Preapplication conference with Administrative
Officer
|
$50/project
| ||
Administrative subdivision
| |||
Application fee
|
$80, plus $75/lot1
| ||
Review fee
|
$50/hour (5-hour minimum)2
| ||
Concept review stage
| |||
Subdivisions
| |||
Application fee
|
$80, plus $50/lot
| ||
Review fee
|
$50/hour (five-hour minimum)2
| ||
Land development projects
|
$50 per unit or acre,2 plus $80
| ||
Application fee
|
$80, plus $50/unit or acre3
| ||
Review fee
|
$50/hour (five-hour minimum)2
| ||
Master plan stage
| |||
Subdivisions
| |||
Application fee
|
$80, plus $75/lot
| ||
Review fee
|
$50/hour (five-hour minimum)2
| ||
Land development projects
| |||
Application fee
|
$80, plus $75/unit or acre3
| ||
Review fee
|
$50/hour (five-hour minimum)2
| ||
Decision (preparation fee)
|
$150/decision
| ||
Preliminary plan stage
| |||
Subdivisions
| |||
Application fee
|
$80, plus $125/lot
| ||
Review fee
|
$50/hour (five-hour minimum)2
| ||
Land development projects
| |||
Application fee
|
$80, plus $125/unit or acre3
| ||
Review fee
|
$50/hour (five-hour minimum)2
| ||
Decision (preparation fee)
|
$150/decision
| ||
Informational meeting preparation fees
| |||
Subdivisions
|
$50, plus $2/each required notice to each addressee
on notification list
| ||
Multifamily and/or residential unit planned
development projects
|
$50, plus $2/each required notice to each addressee
on notification list
| ||
Land development projects
|
$50, plus $2/each required notice to each addressee
on notification list
| ||
Any other project not otherwise listed (requiring
an informational meeting)
|
$50, plus $2/each required notice to each addressee
on notification list
| ||
Public hearing preparation fees
| |||
Subdivisions
|
$50, plus $5/each required notice to each addressee
on notification list
| ||
Multifamily and/or residential unit planned
development projects
|
$50, plus $5/each required notice to each addressee
on notification list
| ||
Land development projects
|
$50, plus $5/each required notice to each addressee
on notification list
| ||
Any other project not otherwise listed (requiring
a public hearing)
|
$50, plus $5/each required notice to each addressee
on notification list
| ||
Final stage
| |||
Subdivisions
| |||
Application fee
|
$80, plus $105/lot
| ||
Review fee
|
$50/hour (five-hour minimum)2
| ||
Land development projects
| |||
Application fee
|
$80, plus $105/unit or acre3
| ||
Review fee
|
$50/hour (five-hour minimum)2
| ||
Decision (preparation fee)
|
$150/decision
| ||
Review for recording for subdivisions [Note:
Town Clerk recording fees are not included.]
|
$80, plus $75/lot
| ||
Review for final filing for land development
projects and any other non-subdivision projects not otherwise addressed
|
$80, plus $75/unit or acre3
| ||
Review of buildable lot applications
|
$300/application
| ||
Review of Town Council referred projects
|
$100/acre3 ($100
minimum)
| ||
Review of Zoning Board of Review referred projects
|
$100/acre3 ($100
minimum)
| ||
Review of Comprehensive Plan proposed land use
map amendment proposals
|
$700/acre3 ($700
minimum)
| ||
Review of Comprehensive Plan proposed text amendment
proposals
|
$1,000
| ||
Review of Town Council Zoning Map amendment
petitions
|
$700/acre3 ($700
minimum)
| ||
Review of Town Council zoning text amendment
petitions
|
$1,000
| ||
Site plan review
| |||
Application for industrial projects
|
$700/acre3
| ||
Application for commercial and business projects
|
$700/acre3
| ||
Application for planned development (PD) projects
|
$300, plus $50/acre,3 plus $25/unit
| ||
Application for nonresidential projects requiring
landscaping review (less than one acre)
|
$250/acre3
| ||
Application for nonresidential projects not
otherwise addressed
|
$700/acre3
| ||
Application for multifamily development and
other residential (non-PD) projects not otherwise addressed
|
$300, plus $50/acre,3 plus $25/unit
| ||
Review fee for all site plan review projects
|
$50/hour (five-hour minimum)2
| ||
Appeal to the Johnston Board of Appeals to a
decision of the Planning Board and/or Administrative Officer
|
$250
| ||
Recording fee for all decisions
|
Actual costs
| ||
Mailing costs for required notifications (actual
mailing costs plus duplication cost of materials and attachments)
[Note: Applicants will be charged for each meeting
where they do not attend the meeting (no-show) or request to be continued
after the notice has been published or are repeatedly incomplete with
their presentation thereby requiring a continuance.]
|
For each meeting, $50, plus duplication and
preparation costs, plus actual mailing costs
| ||
Advertising costs for required notices for public
hearings, including newspaper advertisement
|
Actual costs
| ||
Advertising costs for required monthly meeting
notices
[Note: Applicants will be charged for each meeting
where they do not attend the meeting (no-show) or request to be continued
after the notice has been published or are repeatedly incomplete with
their presentation thereby requiring a continuance.]
|
$50/agenda item
|
NOTES:
| ||
1"Number of lots"
based on highest number of lots before or after the administrative
subdivision.
| ||
2Actual hourly review
costs at five-hour minimum will be charged and collected at time of
application submission; hours spent in excess of five hours will be
billed to the applicant at the actual costs ($50/hour minimum); no
final decision or recording will be completed until all fees have
been paid.
| ||
3"Acres" refers to
acres to be disturbed (rounded up); fee cost is the greater cost based
on the per-unit or per-acre formula cost.
|
Description
|
Fee
| ||
---|---|---|---|
Advisory opinion from Zoning Official/Zoning
Enforcement Officer
|
$100
| ||
Variances, excluding sheds and signs
| |||
Residential uses and zones
| |||
Application fee
|
$80, plus $250/lot or unit1
| ||
Review fee
|
$50/hour (three-hour minimum)2
| ||
Commercial, business, office, industrial, nonresidential
uses and zones
| |||
Total project site's building GFA less than
5,000 square feet
|
Application fee of $1,000, plus review fee of
$50/hour (three-hour minimum)2
| ||
Total project site's building GFA 5,001 to 10,000
square feet
|
Application fee of $1,500, plus review fee of
$50/hour (three-hour minimum)2
| ||
Total project site's building GFA 10,001 to
20,000 square feet
|
Application fee of $2,000, plus review fee of
$50/hour (three-hour minimum)2
| ||
Total project site's building GFA greater than
20,000 square feet
|
Application fee of $100/every 1,000 square feet
of total project site building GFA (prorated, rounded up to nearest
1,000 square feet of GFA), plus review fee of $50/hour (three-hour
minimum)2
| ||
Special use permits
| |||
Residential uses and zones
| |||
Application fee
|
$80, plus $250/lot or unit1
| ||
Review fee
|
$50/hour (three-hour minimum)2
| ||
Commercial, business, office, industrial, nonresidential
uses and zones
| |||
Total project site's building GFA less than
5,000 square feet
|
Application fee of $1,000, plus review fee of
$50/hour (three-hour minimum)2
| ||
Total project site's building GFA 5,000 to 10,000
square feet
|
Application fee of $1,500, plus review fee of
$50/hour (three-hour minimum)2
| ||
Total project site's building GFA 10,001 to
20,000 square feet
|
Application fee of $2,000, plus review fee of
$50/hour (three-hour minimum)2
| ||
Total project site's building GFA greater than
20,000 square feet
|
Application fee of $1,000/every 10,000 square
feet of total project site/building GFA (prorated, rounded up to nearest
1,000 square feet of GFA), plus review fee of $50/hour (three-hour
minimum)2
| ||
Variances — sheds
| |||
Application fee
|
$100/shed
| ||
Review fee
|
$80
| ||
Variances — signs
| |||
Application fee
| |||
First sign in application
|
$500
| ||
Each additional sign in application
|
$100
| ||
Review fee
|
$80
| ||
Appeals
| |||
To Johnston Board of Appeals to a decision of
the Planning Board and/or Administrative Officer
|
$250/decision
| ||
To Johnston Board of Review to a decision of
the Zoning Official/Zoning Enforcement Officer or Building Official
|
$250/decision
| ||
Public hearing preparation fees, all applications
|
$50, plus $5/each required notice to each addressee
on notification list
| ||
Review of buildable lot applications
|
$300/application
| ||
Zoning certificates
| |||
Single-family residential dwelling unit (no
in-law unit)
|
$250/certificate
| ||
Residential property or use, excluding single-family
residential dwelling unit (no in-law unit)
|
$500/certificate, plus $50/hour research cost3 ($50 minimum)
| ||
Nonresidential property or use
|
$1,000/certificate, plus $50/hour research cost3 ($50 minimum)
| ||
Recertification of property within two years
of issuance of previous zoning certificate/
certification
|
$50/certificate, plus $50/hour research cost3 ($50 minimum)
| ||
Decision (preparation)
|
$150/decision
| ||
Recording fee for all decisions
|
Actual recording costs
| ||
Mailing costs for required notifications (actual
mailing costs plus notice preparation cost and duplication cost of
materials and attachments)
[Note: Applicants will be charged for each meeting
where they do not attend the meeting (no-show) or request to be continued
after the notice has been published or are repeatedly incomplete with
their presentation thereby requiring a continuance.]
|
For each meeting, $50, plus duplication and
preparation costs, plus actual mailing costs
| ||
Advertising costs for required additional notices
for public hearings, including newspaper advertisement
|
Actual costs
| ||
Advertising costs for required monthly meeting
notices
[Note: Applicants will be charged for each meeting
where they do not attend the meeting (no-show) or request to be cancel
and continued after the required hearing notice has been published
or are repeatedly incomplete with their presentation thereby requiring
a continuance.]
|
$50/agenda item
|
Notes:
1 “Per unit”
measure shall be sued for residential properties involving two or
more dwelling units. “Per lot” measure shall be used for
residential properties involving one dwelling unit per lot.
2 Actual hourly review
costs, $50/hour minimum fee at three-hour minimum, will be charged
and collected at time of application submission; hours spent in excess
of three hours will be billed to the applicant at the actual costs
($50/hour minimum); no final decision or recording will be completed
until all fees have been paid.
3 Actual hourly research
costs ($50/hour minimum fee) at one-hour minimum will be charged and
collected at time of application submission; hours spent in excess
of one hour will be billed to the applicant at the actual costs ($50/hour
minimum); no final certificate will be completed until all fees have
been paid.
|