In all areas of special flood hazard, the following standards are required:
A. 
Anchoring.
(1) 
All new construction and substantial improvements shall be anchored to prevent flotation, collapse, or lateral movement of the structure and capable of resisting hydrostatic and hydrodynamic loads.
(2) 
All manufactured homes must be elevated and anchored to resist flotation, collapse or lateral movement and capable of resisting the hydrostatic and hydrodynamic loads. Methods of anchoring may include, but are not limited to, use of over-the-top or frame ties to ground anchors. This requirement is in addition to applicable state and local anchoring requirements for resisting wind forces. Specific requirements may be:
(a) 
Over-the-top ties be provided at each of the four corners of the manufactured home, with two additional ties per side at intermediate locations, with manufactured homes less than 50 feet long requiring one additional tie per side;
(b) 
Frame ties be provided at each corner of the home with five additional ties per side at intermediate points, with manufactured homes less than 50 feet long requiring four additional ties per side;
(c) 
All components of the anchoring system be capable of carrying a force of 4,800 pounds; and
(d) 
Any additions to the manufactured home be similarly anchored.
B. 
Construction Materials and Methods.
(1) 
All new construction and substantial improvements shall be constructed with materials and utility equipment resistant to flood damage.
(2) 
All new construction and substantial improvements shall be constructed using methods and practices that minimize flood damage.
(3) 
All new construction and substantial improvements shall be constructed with electrical, heating, ventilation, plumbing, and air-conditioning equipment and other service facilities that are designed and/or located so as to prevent water from entering or accumulating within the components during conditions of flooding.
C. 
Utilities.
(1) 
All new and replacement water supply systems shall be designed to minimize or eliminate infiltration of floodwaters into the system;
(2) 
New and replacement sanitary sewage systems shall be designed to minimize or eliminate infiltration of floodwaters into the systems and discharge from the systems into floodwaters; and
(3) 
On-site waste disposal systems shall be located to avoid impairment to them or contamination from them during flooding.
D. 
Subdivision Proposals.
(1) 
All subdivision proposals shall be consistent with the need to minimize flood damage;
(2) 
All subdivision proposals shall have public utilities and facilities such as sewer, gas, electrical, and water systems located and constructed to minimize flood damage;
(3) 
All subdivision proposals shall have adequate drainage provided to reduce exposure to flood damage;
(4) 
Base flood elevation data shall be provided for subdivision proposals and other proposed development which contain at least 50 lots or five acres (whichever is less); and
(5) 
All proposals for the development of subdivisions including the placement of manufactured home parks and subdivisions shall meet development permit requirements of §§ 7-138, 7-139 and 7-140.
In all areas of special flood hazard where base flood elevation data has been provided as set forth in § 7-136B, Use of Other Base Flood Data, the following standards are required:
A. 
Residential Construction. New construction and substantial improvement of any residential structure shall have the lowest floor (including basement) elevated to or above the base flood elevation.
B. 
Nonresidential Construction. New construction and substantial improvement of any commercial, industrial or other nonresidential structure shall either have the lowest floor (including basement) elevated to the level of the base flood elevation; or, together with attendant utility and sanitary facilities, shall:
(1) 
Be floodproofed so that below the base flood elevation the structure is watertight with walls substantially impermeable to the passage of water;
(2) 
Have structural components capable of resisting hydrostatic and hydrodynamic loads and effects of buoyancy; and
(3) 
Be certified by a registered professional engineer or architect that the design and methods of construction are in accordance with accepted standards of practice for meeting the provisions of this subsection. Such certifications shall be provided to the officials set forth in § 7-135.
C. 
Openings in Enclosures Below the Lowest Floor. For all new construction and substantial improvements, fully enclosed areas below the lowest floor that are subject to flooding shall be designed to automatically equalize hydrostatic flood forces on exterior walls by allowing for the entry and exit of floodwaters. Designs for meeting this requirement must either be certified by a registered professional engineer or architect or must meet or exceed the following minimum criteria:
(1) 
A minimum of two openings having a total net area of not less than one square inch for every square foot of enclosed area subject to flooding shall be provided;
(2) 
The bottom of all openings shall be no higher than one foot above grade;
(3) 
Openings may be equipped with screens, louvers, or other coverings or devices, provided that they permit the automatic entry and exit of floodwaters.
D. 
Manufactured Homes.
(1) 
Manufactured homes shall be anchored in accordance with § 7-138.
(2) 
All manufactured homes or those to be substantially improved shall conform to the following requirements:
(a) 
Require that manufactured homes that are placed or substantially improved on a site outside of a manufactured home park or subdivision, in a new manufactured home park or subdivision, in an expansion to an existing manufactured home park or subdivision or in an existing manufactured home park or subdivision on which a manufactured home has incurred substantial damage as the result of a flood be elevated on a permanent foundation such that the lowest floor of the manufactured home is elevated to or above the base flood elevation and be securely anchored to an adequately anchored foundation system to resist flotation, collapse and lateral movement.
(b) 
Require that manufactured homes to be placed or substantially improved on sites in existing manufactured home park or subdivisions that are not subject to the provisions in Subsection D(2)(a) above be elevated so that either the lowest floor of the manufactured home is at or above the base flood elevation, or the manufactured home chassis is supported by reinforced piers or other foundation elements that are no less than 36 inches in height above grade and be securely anchored to an adequately anchored foundation system to resist flotation, collapse, and lateral movement.
(c) 
Require that all manufactured homes to be placed within Zone A on the City's FHBM or FIRM shall be installed using methods and practices which minimize flood damage. For the purposes of this requirement, manufactured homes must be elevated and anchored to resist flotation, collapse or lateral movement. Methods of anchoring may include, but are not limited to, use of over-the-top or frame ties to ground anchors. This requirement is in addition to applicable state and City anchoring requirements for resisting wind forces.
E. 
Recreational Vehicles.
(1) 
Require that recreational vehicles either be on the site for fewer than 180 consecutive days, be fully licensed and ready for highway use, or meet the permit requirements and elevation and anchoring requirements for manufactured homes as stated in §§ 7-138 and 7-140.
A. 
Located within areas of special flood hazard established in § 7-129 are areas designated as floodways. Since the floodway is an extremely hazardous area due to the velocity of floodwaters which carry debris, potential projectiles, and erosion potential, the following provisions apply:
(1) 
Prohibit encroachments, including fill, new construction, substantial improvements, and other development unless certification by a registered professional engineer or architect is provided demonstrating that encroachments shall not result in any increase in flood levels during the occurrence of the base flood discharge.
(2) 
If Subsection A(1) of this section is satisfied, all new construction and substantial improvements shall comply with all applicable flood hazard reduction provisions of Article XXVI, Provisions for Flood Hazard Reduction.
(3) 
Under the provisions of 44 CFR Chapter 1, § 65.12, of the National Flood Insurance Regulations, the City may permit encroachments within the adopted regulatory floodway that would result in an increase in base flood elevations, provided that the City first applies for a conditional FIRM and floodway revision through FEMA.