This article shall be known and may be cited as the "Land Application of Sewage Sludge Ordinance of Hellam Township, York County, PA of 1996."
A.
The purpose of this article is:
(1)
To protect the health, safety and general welfare of all Township citizens and other persons by seeking to prevent exposure to any toxic or other harmful material contained in sewage sludge including but not limited to, heavy metals, pathogens, radioactivity and toxic and carcinogenic chemicals as provided by Section 503.5 of Subchapter 0, Chapter 1 of Title 40, Code of Federal Regulations.
(2)
To seek to preserve the surface waters and aquifers that contribute to a healthy environment and to seek to preserve the natural environmental quality of all land and its flora and fauna within the Township.
(3)
To seek to preserve and protect agriculture and agriculture related activities and to seek to preserve a productive land base and climate for future generations.
(4)
To register land application sites and the land application process to assure compliance with PA DEP permit requirements and to provide local registration, inspection and enforcement by PA DEP.
B.
Interpretation or implementation of this article shall give priority to the purposes stated in Subsection A over such considerations as economics, efficiency and scheduling factors.
C.
The federal and state government have established regulations for the land application of sewage sludge. These regulations have been incorporated into this article. The following regulations apply to the land application of sewage sludge as of December 1997.
(1)
A person may not apply sewage sludge in a way that will cause surface or groundwater pollution, cause or allow the attraction, harborage or breeding of vectors, cause or allow emissions of any malodorous air contaminants under Pa. Code, Title 25, Section 123.31(b), adversely affect private or public water supplies, or cause any public nuisance. [25 Pa. Code, Chapter 271, Subchapter J, § 271.902(g)]
(2)
No sewage sludge shall be applied to the land where such application shall constitute an environmental or health hazard or otherwise cause a nuisance.
(3)
No properties other than the permitted site shall be exposed to sewage sludge.
(4)
Sewage sludge shall not be deposited on any land in Hellam Township if the sewage sludge exceeds state and federal standards for land application of sewage sludge.
(5)
Soil pH shall be 6.0 or greater prior to the land application and shall be maintained at 6.0 or greater for the life of land application operations and for two additional years following the last application of sludge to the site.
(6)
All sewage sludge applied to land in Hellam Township shall not be applied to the land at a rate that is greater than the agronomic rate. [25 Pa. Code § 271.915(f)]
(7)
Current regulations require that the following crop harvest restrictions for crops grown on sewage sludge sites be followed.
Crops Harvest Period Prohibited | ||
|---|---|---|
Food crops (above soil) | 24 months | |
Food crops (below soil) | 38 months | |
Feed crops (after application) | 30 days | |
Animal grazing (after application) | 60 days | |
D.
This article does not apply to exceptional quality sewage sludge defined by federal and state regulations.