[Amended 10-20-1987 by Ord. No. 1987-20; 3-5-2020 by Ord. No. 2020-5]
A. The applicant shall complete the appropriate sections of the checklist set forth in Chapter
27, Article
III, §
27-30.7, of this Code and submit the same to the administrative officer. If the application is complete, the administrative officer shall transmit the site plans to the Township Engineer and other designated officials and agencies. They shall prepare reports containing recommendations and/or conditions of approval and a certification as to completeness, The administrative officer shall advise the applicant of the certification within 45 days of submission. The applicant is not required to amend the plan until after Consolidated Land Use Board of Mansfield Township action at a public meeting.
B. The Consolidated Land Use Board of Mansfield Township
shall take action on the site plan at a public meeting of the Board
within 45 days of the certification.
C. The Municipal Consolidated Land Use Board of Mansfield
Township shall condition any approval that it grants upon timely receipt
of a favorable report on the application by the County Planning Board
or approval by the County Planning Board by its failure to report
thereon within the required time period.
D. The Consolidated Land Use Board of Mansfield Township
shall either approve, approve with conditions to which the Township
Engineer can certify compliance or disapprove the site plan. In the
event of a disapproval, the Consolidated Land Use Board of Mansfield
Township shall set forth its reasons for the rejection of the plan.
E. After Consolidated Land Use Board of Mansfield Township
approval, the applicant shall submit six sets of the site plan which
conform to the Consolidated Land Use Board of Mansfield Township approval
to the Township Engineer for certification. No building permit shall
be issued or construction commenced unless the final site plan has
been certified by the Township Engineer. No certificate of occupancy
shall be issued nor shall occupancy take place until and unless all
construction and required improvements shall be completed or bonded
for in conformity with the approved site plan and all conditions required
as a part of said approval.