The following improvements shall be installed by the subdivider. The
final plan shall not be approved until final detailed design of the improvements
is approved and the improvements are installed or security to the Borough
Council is provided.
Streets shall be brought to the grades and dimensions drawn on plans, profiles, and cross-sections submitted by the subdivider and approved by the Borough Engineer. The subdivider must install the required utilities and provide, where necessary, adequate subsurface drainage for the streets. The streets shall be designed and constructed to the standards set forth in §§
380-18 and
380-19 of this chapter.
Curbs and sidewalks shall be provided in accordance with the standards set forth in §
380-20 of this chapter.
A storm drainage system shall be provided in accordance with the standards as set forth in §
380-21 of this chapter.
All improvements shall be installed according to a time schedule which
shall be approved by the Borough Council.
At the time each improvement is to be installed and upon its completion,
the subdivider shall notify the Borough Council so that adequate inspections
can be made. The inspection will be made by the Borough Engineer. All costs
of undertaking the inspection will be borne by the subdivider.