Regardless of whether generators are to be serviced by natural gas,
diesel, propane or gasoline, application must be made to the Building
Department on forms provided by the Borough.
If the premises is a condominium, a letter of approval from the condominium
association granting approval shall be required prior to issuance
of a permit.
A copy of the manufacturer's specifications shall be provided,
to include the size of the generator and with all required clearances
to building structures, trees, shrubs, roof overhangs, doors, windows,
wall air conditioners and wall openings and vents.
A concrete pad or impervious concrete paving stone for placement
of the generator shall be provided. The pad dimension shall be a minimum
of six inches larger than the generator unit on all sides or according
to the generator manufacturer's specifications, whichever requirement
is more stringent.
Portable generators require a permit for the male receptacles, transfer
switch or interlock on the existing panel. The interlock must be listed
and labeled by a recognized testing lab. (A cut sheet shall be provided
for the interlock.)