Certificates of subdivision approval shall be
issued by the Borough Clerk in accordance with N.J.S.A. 40:55D-56
of the Municipal Land Use Law. A fee of $10 shall be charged for each
certificate of approval.
[Amended 12-17-2002 by Ord. No. 2002-752; 12-21-2004 by Ord. No. 2004-781]
A.
Building permits. No building permit shall be issued
by the Construction Official until final approval has been granted
on an application for development.
B.
Certificates of occupancy.
(1)
No land or new construction shall be occupied or used
in whole or in part for any purpose whatsoever until a certificate
of occupancy has been issued by the Construction Official stating
that the use of the land or building complies with the provisions
of this chapter.
(2)
No certificate of occupancy for any land or structure
shall be granted until all required improvements or conditions of
approval have been met, installed or completed. A temporary certificate
of occupancy may be issued but only for a specific period, upon such
conditions as the Borough Engineer may impose, such as bonding, to
ensure the completion or installation of any such improvements unfinished
because of weather or unforeseen delay. The installation of any required
public or private improvements may also be delayed if the Borough
Engineer warrants in writing to the Construction Official that the
delay is in the best interests of the Borough.
C.
Zoning permits. Where an application for development
does (or does not) require a building permit, the Zoning Officer shall
review the application for development and issue a zoning permit upon
payment of the required fee of $85.
[Amended 4-16-1996 by Ord. No. 96-657; 8-17-1999 by Ord. No.
99-703; 8-20-2013 by Ord. No. 2013-937; 3-4-2014 by Ord. No.
2014-947]
Fees for applications or for the rendering of
any service by the Boards or any member of their administrative staffs
shall be as shown below:
Schedule of Fees
| |||||
---|---|---|---|---|---|
Type
|
Fee
|
Initial Escrow for Professional Review
| |||
Land use procedures fee for furnishing list
of property owners
|
$10
| ||||
Planning Board fees
| |||||
Conditional use application
|
$500
|
$2,000
| |||
Townhouse, additional per unit
|
$100
|
$400
| |||
Site plan
| |||||
Preliminary
| |||||
Minimum
|
$400
|
$2,000
| |||
0 to 1,000 square feet of gross floor area
|
$400
|
$2,000
| |||
1,000 to 2,500 square feet of gross floor area
|
$500
|
$2,000
| |||
2,500 to 5,000 square feet of gross floor area
|
$700
|
$2,000
| |||
Over 5,000 square feet of gross floor area
|
$1,000
|
$2,500
| |||
Final
|
1/2 preliminary
|
1/2 preliminary
| |||
Major subdivision
| |||||
Minimum
|
$550
|
$2,000
| |||
Plus per lot
|
$150
|
$550
| |||
Minor subdivision (one-family residential)
| |||||
No new lot created
|
$250
|
$1,000
| |||
1 to 3 lots
|
$500
|
$2,000
| |||
Minor subdivision (other, residential or commercial)
| |||||
1 to 3 lots
|
$250 per lot
|
$2,000
| |||
Special meeting at request of applicant
|
$800
| ||||
Residential application (one- or two-family)
| |||||
Relief pursuant to N.J.S.A. 40:55D-60b or c
|
$100
|
$2,000
| |||
Zoning Board of Adjustment fees
| |||||
Residential application (one- or two-family)
| |||||
Relief pursuant to N.J.S.A. 40:55D-70a, b or
c (appeals, interpretations and "hardship variances")
|
$250
|
$2,000
| |||
Relief pursuant to N.J.S.A. 40:55D-70d ("use
variances")
|
$750
|
$2,500
| |||
Sign
|
$150
| ||||
All other applications
|
$500
|
$1,000
| |||
Special meeting at request of applicant
|
$800
| ||||
Fees for copies of certain ordinances:
| |||||
Site Plan Review Ordinance
|
$6
| ||||
Subdivision Ordinance
|
$7
| ||||
Master Plan
|
$50
| ||||
Zoning Ordinance
|
$50
| ||||
Site plan
| |||||
Preliminary
| |||||
Minimum
|
$400
|
$2,000
| |||
0 to 1,000 square feet of gross floor area
|
$400
|
$2,000
| |||
1,000 to 2,500 square feet of gross floor area
|
$500
|
$2,000
| |||
2,500 to 5,000 square feet of gross floor area
|
$700
|
$2,000
| |||
Over 5,000 square feet of gross floor area
|
$1,000
|
$2,500
| |||
Final
|
1/2 preliminary
|
1/2 preliminary
| |||
Major subdivision
| |||||
Minimum
|
$500
|
$2,000
| |||
Plus per lot
|
$150
|
$550
| |||
Minor subdivision (one-family residential)
| |||||
No new lot created
|
$250
|
$1,000
| |||
1 to 3 lots
|
$500
|
$2,000
| |||
Minor subdivision (other, residential or commercial)
| |||||
1 to 3 lots
|
$250 per lot
|
$2,000
|