Specific definitions. As used in this article, the following terms
shall have the meanings indicated:
ACCESSORY USE OR STRUCTURE
A use or structure on the same lot with, and/or having a
nature customarily incidental and subordinate to, the principal use
or structure.
BASE FLOOD
A flood which has a one-percent chance of being equaled or
exceeded in any given year (also called the "one-hundred-year flood").
BASE FLOOD ELEVATION (BFE)
The elevation shown on the Flood Insurance Rate Map (FIRM)
for Zones AE, AH and A1-30 that indicates the water surface elevation
resulting from a flood that has a one-percent or greater chance of
being equaled or exceeded in any given year. The BFE is also shown
on the FIS profile and can be determined for Zone A floodplains.
BASEMENT
Any area of the building having its floor below ground level
on all sides.
BUILDING
A combination of materials to form a permanent structure
having walls and a roof. Included shall be all manufactured homes
and trailers to be used for human habitation.
COMPLETELY DRY SPACE
A space which will remain totally dry during flooding; the
structure is designed and constructed to prevent the passage of water
and water vapor.
DEVELOPMENT
Any man-made change to improved or unimproved real estate,
including but not limited to the construction, reconstruction, renovation,
repair, expansion, or alteration of buildings, or other structures;
the placement of manufactured homes; streets, and other pavings; utilities;
filling, grading, and excavation; mining; dredging; drilling operations;
storage of equipment or materials; and the subdivision of land.
ESSENTIALLY DRY SPACE
A space which will remain dry during flooding, except for
the passage of some water vapor or minor seepage; the structure is
substantially impermeable to the passage of water.
EXISTING MANUFACTURED HOME PARK OR SUBDIVISION
A manufactured home park or subdivision for which the construction
of facilities for servicing the lots on which the manufactured homes
are to be affixed (including, at a minimum, the installation of utilities,
the construction of streets, and either final site grading or the
pouring of concrete pads) is completed before the effective date of
the floodplain management regulations adopted by a community.
EXPANSION TO AN EXISTING MANUFACTURED HOME PARK OR SUBDIVISION
The preparation of additional sites by the construction of
facilities for servicing the lots on which the manufactured homes
are to be affixed (including the installation of utilities, the construction
of streets, and either final site grading or the pouring of concrete
pads).
FLOOD
A temporary inundation of normally dry land areas.
FLOOD INSURANCE RATE MAP (FIRM)
The official map on which the Federal Emergency Management
Agency has delineated both the areas of special flood hazard and the
risk premium zones applicable to the community.
FLOOD INSURANCE STUDY (FIS)
The official report provided by the Federal Insurance Administration
that includes flood profiles, the Flood Insurance Rate Map, the Flood
Boundary and Floodway Map, and the water surface elevation of the
base flood.
FLOODPLAIN AREA
A relatively flat or low land area which is subject to partial
or complete inundation from an adjoining or nearby stream, river,
or watercourse; and/or any area subject to the unusual and rapid accumulation
of surface waters from any source.
FLOODPROOFING
Any combination of structural and nonstructural additions,
changes, or adjustments to structures which reduce or eliminate flood
damage to real estate or improved real property, water, and sanitary
facilities, structures and their contents.
FLOOD-RESISTANT MATERIALS
Flood-resistant material includes any building product capable
of withstanding direct and prolonged contact with floodwaters without
sustaining significant damage. Prolonged contact means at least 72
hours. Significant damage is any damage requiring more than low-cost
cosmetic repair (such as painting). All structural and nonstructural
building materials at or below the base flood elevation (BFE) must
be flood-resistant.
FLOODWAY
The designed area of a floodplain required to carry and discharge
floodwaters of a given magnitude. For the purposes of this article,
the floodway shall be capable of accommodating a flood of the one-hundred-year
magnitude.
FLOODWAY FRINGE
That part of the floodplain adjacent to and extending from
the floodway and subject to inundation by the one-hundred-year flood.
FREEBOARD
A factor of safety usually expressed in feet above a flood
level for purposes of floodplain management.
HIGHEST ADJACENT GRADE
The highest natural elevation of the ground surface prior
to construction next to the proposed walls of a structure.
HISTORIC STRUCTURE
Any structure that is:
(1)
Listed individually in the National Register of Historic Places
(a listing maintained by the Department of the Interior) or preliminarily
determined by the Pennsylvania Historic and Museum Commission (PHMC)
as meeting the requirements for individual listing on the National
Register.
(2)
Certified or preliminarily determined by the Pennsylvania Historic
and Museum Commission (PHMC) as contributing to the historical significance
of a registered historic district or a district preliminarily determined
by the PHMC to qualify as a registered historic district.
IDENTIFIED FLOODPLAIN AREA
The floodplain area specifically identified in this article
as being inundated by the one-hundred-year flood.
LAND DEVELOPMENT
Any of the following activities:
(1)
The improvement of one lot or two or more contiguous lots, tracts,
or parcels of land for any purpose involving:
(a)
A group of two or more residential or nonresidential buildings,
whether proposed initially or cumulatively, or a single nonresidential
building on a lot or lots, regardless of the number of occupants or
tenure.
(b)
The division or allocation of land or space, whether initially
or cumulatively, between or among two or more existing or prospective
occupants by means of, or for the purpose of, streets, common areas,
leaseholds, condominiums, building groups, or other features.
LOWEST FLOOR
The lowest floor of the lowest fully enclosed area (including
basement). An unfinished, flood-resistant partially enclosed area,
used solely for parking of vehicles, building access, and incidental
storage, in an area other than a basement area is not considered the
lowest floor of a building, provided that such space is not designed
and built so that the structure is in violation of the applicable
nonelevation design requirements of this article.
MANUFACTURED HOME
A transportable, single-family dwelling intended for permanent
occupancy, an office, or a place of assembly, contained in one or
more sections, built on a permanent chassis, which arrives at a site
completed and ready for occupancy except for minor and incidental
unpacking and assembling operations, and constructed so that it may
be used with or without a permanent foundation. The term includes
mobile home, park trailers, travel trailers, and recreational and
other similar vehicles which are placed on a site for more than 180
consecutive days.
MANUFACTURED HOME PARK
A parcel of land under single ownership which has been planned
and improved for the placement of two or more manufactured homes for
nontransient use.
MINOR REPAIR
The replacement of existing work with equivalent materials
for the purpose of its routine maintenance and upkeep, but not including
the cutting away of any wall, partition or portion thereof, the removal
or cutting of any structural beam or bearing support, or the removal
or change of any required means of egress, or rearrangement of parts
of a structure affecting the exitway requirements; nor shall minor
repairs include addition to, alteration of, or replacement or relocation
of any standpipe, water supply, sewer, drainage, drain leader, gas,
oil, waste, vent, or similar piping, electric wiring or mechanical
or other work affecting public health or general safety.
NEW CONSTRUCTION
Structures for which the start of construction commenced
on or after March 2, 2016, and includes any subsequent improvements
thereto. Any construction started after September 30, 1977, and before
March 2, 2016 (the effective start date of this floodplain management
article), is subject to the ordinance in effect at the time the permit
was issued, provided the start of construction was within 180 days
of permit issuance.
NEW MANUFACTURED HOME PARK OR SUBDIVISION
A manufactured home park or subdivision for which the construction
of facilities for servicing the lots on which the manufactured homes
are to be affixed (including, at a minimum, the installation of utilities,
the construction of streets, and either final site grading or the
pouring of concrete pads) is completed on or after the effective date
of floodplain management regulations adopted by a community.
ONE-HUNDRED-YEAR FLOOD
A flood that, on the average, is likely to occur once every
100 years (i.e., that has a one-percent chance of occurring each year,
although the flood may occur in any year). Also referred to as the
"one-percent-frequency flood" or the "base flood," as defined by FEMA
in the Flood Insurance Study for Lower Frederick Township.
PERSON
An individual, partnership, public or private association
or corporation, firm, trust, estate, municipality, governmental unit,
public utility, or any other legal entity whatsoever, which is recognized
by law as the subject of rights and duties.
POST-FIRM STRUCTURE
A structure for which construction or substantial improvement
occurred after September 30, 1977, the date of the initial FEMA Flood
Insurance Rate Map, and, as such, would be required to be compliant
with the regulations of the NFIP.
PRE-FIRM STRUCTURE
A structure for which construction or substantial improvement
occurred on or before September 30, 1977, the date of the initial
FEMA Flood Insurance Rate Map, and, as such, would not be required
to be compliant with the regulations of the NFIP.
RECREATIONAL VEHICLE
A vehicle which is: built on a single chassis; not more than
400 square feet, measured at the largest horizontal projections; designed
to be self-propelled or permanently towable by a light-duty truck;
and not designed for use as a permanent dwelling but as temporary
living quarters for recreational, camping, travel, or seasonal use.
REGULATORY FLOOD ELEVATION
The regulatory flood elevation is the elevation to which
development is regulated for purposes of elevation and/or dry floodproofing.
It is equal to the base flood elevation (BFE) plus a freeboard of
1 1/2 feet.
REPETITIVE LOSS
Flood-related damages sustained by a structure on two separate
occasions during a ten-year period for which the cost of repairs at
the time of each such flood event, on average, equals or exceeds 25%
of the market value of the structure before the damages occurred.
SPECIAL FLOOD HAZARD AREA (SFHA)
An area in the floodplain subject to a one-percent or greater
chance of flooding in any given year. It is shown on the FIRM as Zone
A, AO, A1-A30, AE, A99, or AH.
SPECIAL FLOODPLAIN AREA
The areas identified as Zone AE in the Flood Insurance Study,
where one-hundred-year flood elevations have been provided, but no
floodway has been delineated.
SPECIAL PERMIT
A special approval which is required for hospitals, nursing
homes, jails, and new manufactured home parks and subdivisions and
substantial improvements to such existing parks, when such development
is located in all, or a designed portion, of a floodplain.
START OF CONSTRUCTION
The date the permit was issued for substantial improvement
and other proposed new development, provided the actual start of construction,
repair, reconstruction, rehabilitation, addition, placement, or other
improvement was within 180 days from the date of the permit and shall
be completed within 12 months after the date of issuance of the permit
unless a time extension is granted, in writing, by the Floodplain
Administrator. The "actual start" means either the first placement
of permanent construction of a structure on a site, such as the pouring
of slab or footings, the installation of piles, the construction of
columns, or any work beyond the stage of excavation; or the placement
of a manufactured home on a foundation. Permanent construction does
not include land preparation, such as clearing, grading, and filling;
nor does it include the installation of streets and/or walkways; nor
does it include excavation for a basement, footings, piers, or foundations
or the erection of temporary forms; nor does it include the installation
on the property of accessory buildings, such as garages or sheds not
occupied as dwelling units or not part of the main structure. For
a substantial improvement, the "actual start of construction" means
the first alteration of any wall, ceiling, floor, or other structural
part of a building, whether or not that alteration affects the external
dimensions of the building.
STRUCTURE
A walled and roofed building, including a gas or liquid storage
tank that is principally above ground, as well as a manufactured home.
SUBDIVISION
The division or redivision of a lot, tract, or parcel of
land by any means into two or more lots, tracts, parcels, or other
divisions of land, including changes in existing lot lines, for the
purpose, whether immediate or future, of lease, partition by the court
for distribution to heirs or devisees, transfer of ownership or building
or lot development; provided, however that the subdivision by lease
of land for agricultural purposes into parcels of more than 10 acres,
not involving any new street or easement of access or any residential
dwelling, shall be exempted.
SUBSTANTIAL DAMAGE
Damage from any cause sustained by a structure whereby the
cost of restoring the structure to its before-damaged condition would
equal or exceed 50% or more of the market value of the structure before
the damage occurred.
SUBSTANTIAL IMPROVEMENT
Any reconstruction, rehabilitation, addition, or other improvement
of a structure, the cost of which equals or exceed 50% of the market
value of the structure before the start of construction of the improvement.
This term includes structures which have incurred substantial damage,
regardless of the actual repair work performed. The term does not,
however, include either:
(1)
Any project for improvement of a structure to correct existing
violations of state or local health, sanitary, or safety code specifications
which have been identified by the local code enforcement official
and which are the minimum necessary to assure safe living conditions.
(2)
Any alteration of an historic structure, provided that the alteration
will not preclude the structure's continued designation as an historic
structure.
UNIFORM CONSTRUCTION CODE (UCC)
The statewide building code adopted by The Pennsylvania General
Assembly in 1999 applicable to new construction in all municipalities,
whether administered by the municipality, a third party or the Department
of Labor and Industry. Applicable to residential and commercial buildings,
the code adopted the International Residential Code (IRC) and the
International Building Code (IBC), by reference, as the construction
standard applicable with the state floodplain construction. For coordination
purposes, references to the above are made specifically to various
sections of the IRC and the IBC.
VIOLATION
The failure of a structure or other development to be fully
compliant with the community's floodplain management regulations.
A structure or other development without the elevation certificate,
other certifications, or other evidence of compliance required in
44 CFR 60.3(b)(5), (c)(4), (c)(10), (d)(3), (e)(2), (e)(4), or (e)(5)
is presumed to be in violation until such time as that documentation
is provided.