The Town will release from the letter of credit, upon
satisfactory and approved installation of the sanitary and storm sewers,
60% of the money allocated for these items in the letter of credit.
After approved lamping, testing, cleaning, and sealing of manholes,
an additional 30% of the money set aside will be released. Sewers
may not be tested and lamped until the completion of rough road boxing,
but shall be done prior to the placement of road materials. Any pipe
repair work must be done in an approved manner by using acceptable
patented repair sleeves or by removing and replacing damaged pipe.
Repairs to sanitary sewers by using concrete patches or other inferior
workmanship will not be permitted.