A. 
When the developer has completed all of the necessary and appropriate improvements, the developer shall notify the Board of Supervisors in writing, by certified or registered mail, of the completion of the aforesaid improvements and shall send a copy thereof to the Township Engineer. The Board of Supervisors shall, within 10 days after receipt of such notice, direct and authorize the Township Engineer to inspect all of the aforesaid improvements. The Township Engineer shall thereupon file a report, in writing, with the Board of Supervisors, and shall promptly mail a copy of the same to the developer by certified or registered mail. The report shall be made and mailed within 30 days after receipt by the Township Engineer of the aforesaid authorization from the Board of Supervisors; said report shall be detailed and shall indicate approval or rejection of said improvements, either in whole or in part, and if said improvements, or any portion thereof, shall not be approved or shall be rejected by the Township Engineer, said report shall contain a statement of reasons for such nonapproval or rejection.
B. 
The Board of Supervisors shall notify the developer, within 15 days of receipt of the engineer's report, in writing by certified or registered mail of the action of the Board of Supervisors with relation thereto.
C. 
If the Board of Supervisors or the Township Engineer fails to comply with the time limitation provisions contained herein, all improvements will be deemed to have been approved and the developer shall be released from all liability, pursuant to its performance guaranty bond or other security agreement.
D. 
If any portion of the said improvements shall not be approved or shall be rejected by the Board of Supervisors, the developer shall proceed to complete the same and, upon completion, the same procedure of notification as outlined herein shall be followed.
E. 
Nothing herein, however, shall be construed in limitation of the developer's right to contest or question, by legal proceeding or otherwise, any determination of the Board of Supervisors or the Township Engineer.
In the event that any improvements which may be required have not been installed as provided in this chapter or in accord with the approved final plan, the Board of Supervisors is hereby granted the power to enforce any corporate bond, or other security by appropriate legal and equitable remedies. If proceeds of such bond or other security are insufficient to pay the cost of installing or making repairs or corrections to all the improvements covered by said security, the Board of Supervisors may, at its option, install part of such improvements in all or part of the subdivision or land development and may institute appropriate legal or equitable action to recover the monies necessary to complete the remainder of the improvements. All of the proceeds, whether resulting from the security or from any legal or equitable action brought against the developer, or both, shall be used solely for the installation of the improvements covered by such security, and not for any other municipal purpose.
A. 
The applicant of a development or subdivision plan shall reimburse the Township for the reasonable and necessary expense incurred as a result of the inspection of improvements required by a subdivision or land development plan. The reimbursement costs shall be based on a cost schedule established by resolution. Such expense shall be reasonable and in accordance with the ordinary and customary fees charged by the Township Engineer or professional consultant for similar services in the community, but in no event shall the fees exceed the rate or cost of the consultant or engineer to the Township when fees are not reimbursed for otherwise imposed on applicants.
B. 
The Township shall advise the applicant of the reimbursement amount required within 30 days of being billed by the Township Engineer and/or professional consultant. The applicant shall provide reimbursement to the Township within 30 days of receipt of the notice of payment due.
C. 
In the event the applicant disputes the amount of any such expense in connection with the inspection of improvements, the applicant shall within 10 working days of the date of billing, notify the Township that such expenses are disputed as unreasonable or unnecessary, in which case the Township shall not delay or disapprove a subdivision or land development application or any approval or permit related to development due to the applicant's request over disputed engineer expenses.
D. 
If, within 20 days from the date of billing, the Township and the applicant cannot agree on the amount of expenses which are reasonable and necessary, then the applicant and Township shall jointly, by mutual agreement, appoint another professional engineer licensed as such in the Commonwealth of Pennsylvania to review the said expenses and make a determination as to the amount thereof which is reasonable and necessary.
E. 
The professional engineer so appointed shall hear such evidence and review such documentation as the professional engineer in his or her sole opinion deems necessary and render a decision within 50 days of the billing date. The applicant shall be required to pay the entire amount determined in the decision immediately.
F. 
In the event that the Township and applicant cannot agree upon the professional engineer to be appointed within 20 days of the billing date, then, upon application of either party, the President Judge of the Court of Common Pleas of Dauphin County, or, if at the time there is no President Judge, then the senior active judge then sitting shall appoint such engineer who, in that case, shall be neither the Township Engineer nor any professional engineer who has been retained by, or performed services for, the Township or the applicant within the preceding five years.
G. 
The fee of the appointed professional engineer for determining the reasonable and necessary expenses shall be paid by the applicant if the amount of payment required in the decision is equal to or greater than the original bill. If the amount of payment required in the decision is less than the original bill by $1,000 or more, the Township shall pay the fee of the professional engineer, but otherwise the Township and the applicant shall each pay 1/2 of the fee of the appointed professional engineer.