No building permit shall be issued by the Construction
Official for any proposed structure unless and until the Township
Engineer shall have approved a detailed site grading plan submitted
in accordance with this chapter. If the proposed land disturbance
as shown on the detailed site grading plan extends beyond the limit
of land disturbance as shown on an approved soil erosion and sediment
control plan, no permit will be issued, and the applicant shall apply
to the appropriate Board for approval to amend the lot grading plan
and soil erosion and sediment control plan. Upon approval or denial
of any site grading plan required by this chapter, the Secretary of
the Planning Board shall forthwith notify the Construction Official
thereof.
No certificate of occupancy shall be issued
by the Construction Official unless and until proof has been submitted
to him/her or her that all conditions of the site grading plan approval
have been fully met and complied with, including verification of compliance
from the Township Engineer that there has been no land disturbance
beyond the limit of land disturbance as shown on the approved detailed
grading plan and soil erosion and sediment control plan.