All subdivision and land development activities involving an increase in impervious cover (i.e., reduction in permeability) shall be conducted in conformance with the following standards:
A. 
After installation of impervious cover, peak discharges for the one-, ten-, twenty-five-, and one-hundred-year frequency storms from the site shall not exceed the respective peak discharge performance standards in Appendix A, Section VI.[1]
[1]
Editor’s Note: Said appendix is on file and available for inspection in the Loyalsock Township office.
B. 
Stormwater runoff shall be managed so that no downstream increases in flood damages or impairment of streets and other public facilities occur. The Municipal Engineer may require that downstream impacts be evaluated at critical locations such as dams, tributaries, existing developments, undersized culverts, and floodprone areas. The municipality and its Engineer shall make the final determination with respect to the degree of management required for any site. The applicant shall evaluate the effects of the proposed plan on such critical locations by providing computed water surface elevations (WSEL) for the ten- and one-hundred-year storms. Methods of computation shall have prior approval of the Municipal Engineer. At such downstream critical locations, stormwater management may be exercised by:
(1) 
Providing off-site improvements to downstream conveyances in order to contain flow increases.
(2) 
Providing downstream drainage easements with sufficient widths to contain the flood limits.
C. 
Groundwater recharge and water quality for regulated earth disturbance activities.
[Amended 3-22-2005 by Ord. No. 311]
(1) 
No regulated earth disturbance activities within the municipality shall commence until approval by the municipality of a plan which demonstrates compliance with state water quality requirements after construction is complete. Appendix D provides the procedure for determining groundwater recharge and water quality requirements.[2]
[2]
Editor’s Note: Said appendix is on file and available for inspection in the Loyalsock Township office.
(2) 
Maximizing the groundwater recharge capacity of the area being developed is required.
(3) 
The BMPs must be designed to protect and maintain existing uses (e.g., drinking water use; cold water fishery use) and maintain the level of water quality necessary to protect those uses in all streams, and to protect and maintain water quality in "Special Protection" streams, as required by statewide regulations at 25 Pa. Code Chapter 93 (collectively referred to herein as "state water quality requirements").
(4) 
To control post-construction stormwater impacts from regulated earth disturbance activities, state water quality requirements can be met by BMPs, including site design, which provide for replication of pre-construction stormwater infiltration and runoff conditions, so that post-construction stormwater discharges do not degrade the physical, chemical or biological characteristics of the receiving waters. As described in the DEP Comprehensive Stormwater Management Policy (#392-0300-002, September 28, 2002), this may be achieved by the following:
(a) 
Infiltration: replication of pre-construction stormwater infiltration conditions;
(b) 
Treatment: use of water quality treatment BMPs to ensure filtering out of chemical and physical pollutants from the stormwater runoff; and
(c) 
Streambank and streambed protection: management of volume and rate of post-construction stormwater discharges to prevent physical degradation of receiving waters (e.g., from scouring and erosion).
(5) 
DEP has regulations that require municipalities to ensure design, implementation and maintenance of best management practices ("BMPs") that control runoff from new development and redevelopment (hereinafter "development") after regulated earth disturbance activities are complete. These requirements include the need to implement post-construction stormwater BMPs with assurance of long-term operations and maintenance of those BMPs.
(6) 
Evidence of any necessary permit(s) for regulated earth disturbance activities from the appropriate DEP regional office or County Conservation District must be provided to the municipality.
D. 
In establishing the watershed conditions for calculating stormwater runoff prior to development, the following assumptions shall apply:
(1) 
Woodland or meadow in good condition shall be used for all undeveloped areas.
(2) 
Average antecedent moisture conditions as defined by the Natural Resource Conservation Service.
(3) 
Drainage area reductions equal to the area of undrained depressions or pond factor adjustments in accordance with the Urban Hydrology for Small Watersheds, Technical Release No. 55 (TR-55, USDA, NRCS) procedure shall be applied in determining predevelopment peak discharges from Karst geologic areas.
E. 
Hydrologic methods. All plans and designs for stormwater management facilities shall be reviewed by the Municipal Engineer. Plans for facilities other than storm sewers should determine stormwater peak discharge and stormwater runoff by the use of the Soil Cover Complex Method as set forth in TR-55, and Technical Release No. 20 (TR-20) with specific attention given to antecedent moisture conditions, flood routing, and peak discharge specifications included therein and in the National Engineering Handbook, Section 4, both by U.S. Department of Agriculture, Natural Resource Conservation Service. The Municipal Engineer may permit the use of the Modified Rational Method or other methods for calculation of the storage capacity of a stormwater management facility from drainage areas of 20 acres or less.
(1) 
Coefficients. Acceptable runoff coefficient values for use in the Rational Method equation, and permissible curve numbers for TR 55, maximum velocities, and suggested roughness coefficients and permissible velocities for channels are identified in Tables A-2 through A-5 of Appendix A, Section I of this chapter.[3] When applying the Rational Method coefficients in Table A-3, open space coefficients shall be used for undeveloped, densely vegetated (nonforest) areas instead of meadow coefficients.
[3]
Editor’s Note: Said appendix is on file and available for inspection in the Loyalsock Township office.
(2) 
The Rational Method may be used in lieu of the Soil Cover Complex Method to compute design flows for the sizing of storm sewers, inlets, and swales. Methods approved by the Pennsylvania Department of Transportation and/or Department of Environmental Protection may be used to design the waterway areas of bridges.
(3) 
Rainfall amounts for the return periods specified shall be determined using the Pennsylvania Department of Transportation Intensity Duration Frequency Curves presented in Figure A-1 of Appendix A, Section Iof this chapter.[4] Rainfall duration for hydrograph generation shall be selected for the specified recurrence intervals on the basis of twice the computed time of concentration for the given watershed and subwatersheds. In no case shall the duration be less than one hour.
[4]
Editor’s Note: Said appendix is on file and available for inspection in the Loyalsock Township office.
(4) 
Time of concentration shall be determined in accordance with the method presented in TR-55.
(5) 
In order to reduce stormwater runoff volumes from developed areas and encourage groundwater recharge, underground basin drains, infiltration trenches, and cisterns are permitted, to which roof leaders may be connected. These drains consist of stone-filled basins which temporarily store and release water below ground surface. Plans for such facilities shall be submitted to the municipality for approval, and the basins shall be used only in those areas where soils, geologic, and water table conditions permit. Performance criteria which govern the location, design, construction, and maintenance of these infiltration facilities are contained in Appendix A, Section IV of this chapter.[5] Suggested guidelines are contained in Standards and Specifications for Infiltration Practices (MD DNR).
[5]
Editor’s Note: Said appendix is on file and available for inspection in the Loyalsock Township office.
F. 
Stormwater management facilities and related installations shall be provided:
(1) 
To permit unimpeded flow of natural watercourses. Such flow may be redirected as required, subject to the approval of the Pennsylvania Department of Environmental Protection and the municipality.
(2) 
To insure adequate drainage of all low points along the curbline of streets.
(3) 
To intercept stormwater runoff along streets at intervals reasonably related to the extent and grade of the area drained, and to prevent substantial flow of water across intersections or flooded intersections during storms, in accordance with the procedures contained in the Pennsylvania Department of Transportation Design Manual Part 2, DM-2, Chapter 10 (PennDOT).
(4) 
To insure adequate and unimpeded flow of stormwater under driveways in, near, or across natural watercourses or drainage swales. Suitable pipes or other waterways shall be provided as necessary.
(5) 
To properly drain stormwater runoff from all land development projects. All lot and open areas shall be designed to drain to the nearest practical street or drainage system, existing or proposed, as defined by the Municipal Engineer, with no impact on adjoining properties, unless an area specifically designed for stormwater detention is provided.
G. 
Storm sewers and related installations:
(1) 
Storm sewers, where required by zoning and land use densities, shall be placed under or immediately adjacent to the roadway side of the curb, or as directed by the municipality, when parallel to the street within the right-of-way.
(a) 
When located in undedicated land, they shall be placed within a drainage easement not less than twenty-feet wide as approved by the Municipal Engineer.
(b) 
The use of properly designed, graded, and turfed drainage swales is encouraged in lieu of storm sewers in commercial and industrial areas and, where approved by the Municipal Engineer, in residential areas. Such swales shall be designed not only to carry the required discharge without excessive erosion but also to increase the time of concentration, reduce the peak discharge and velocity, and permit the water to percolate into the soil, where appropriate. Criteria related to the use and design of drainage swales are contained in Appendix A, Section II of this chapter.[6]
[6]
Editor’s Note: Said appendix is on file and available for inspection in the Loyalsock Township office.
(2) 
The design capacity of storm sewers shall be in accordance with Urban Drainage Design Manual, Hydraulic Engineering Circular Number 22 (US DOT, FHA). Storm drainage systems shall be designed without surcharging inlets to provide conveyance of stormwater runoff into a detention basin or similar facility utilized to manage the rate of stormwater runoff. To avoid surcharging inlets, and to ensure that inlets will receive stormwater runoff, the hydraulic grade line at the inlet should be at least six inches below the elevation of the inlet grate. Where site grading will direct stormwater runoff from the one-hundred-year design storm to a detention basin or similar facility utilized to manage the rate of stormwater runoff, then the storm sewer may be designed for the ten-year-design storm. Where site grading will not direct stormwater runoff from the one-hundred-year design storm to a detention basin or similar facility utilized to manage the rate of stormwater runoff, then the storm sewer shall be designed for the one-hundred-year-design storm. Conveyance of storms to the detention basin, up to and including the one-hundred-year frequency, shall be provided so as not to endanger life or seriously damage property.
(3) 
Storm inlet types and inlet assemblies shall conform to the Pennsylvania Department of Transportation Standards for Roadway Construction as approved by the Municipal Engineer.
(a) 
Inlets shall, at a minimum, be located at the lowest point of street intersections, to intercept the stormwater before it reaches pedestrian crossings, or at sag points of vertical curves in the street alignment which provide a natural point of ponding of surface stormwater.
(b) 
Where the municipality deems it necessary because of special land requirements, special inlets may be approved.
(c) 
The interval between inlets collecting stormwater runoff shall be determined in accordance with the Pennsylvania Department of Transportation Design Manual Part 2, DM-2, Chapter 10, Section 5, Capacity of Waterway Areas, or Urban Drainage Design Manual (HEC-22, US DOT, FHA).
(d) 
In curbed sections, the maximum encroachment of water on the roadway pavement shall not exceed 1/2 of a through-traffic lane or one inch less than the depth of curb during the ten-year design storm of five-minute duration. Inlets shall be provided to limit the encroachment of water on the pavement. When inlets are used in a storm system within the right-of-way limits of a street in lieu of manholes, the spacing of such inlets shall not exceed the maximum distance of 450 feet.
(e) 
The design of storm inlets shall be in accordance with Drainage of Highway Pavements, Hydraulic Engineering Circular Number 12, (US DOT, FHA).
(4) 
Accessible drainage structures shall be located on a continuous storm sewer system at all vertical dislocations, at all locations where a transition in storm sewer pipe sizing is required, at all vertical and horizontal angle points exceeding 5°, and at all points of convergence of two or more influent storm sewer mains. The construction locations of accessible drainage structures shall be as indicated on the subdivision drainage plan or area drainage plan approved by the municipality.
(5) 
When evidence available to the municipality indicates that existing storm sewers have sufficient capacity as determined by hydrograph summation and are accessible, proposed stormwater facilities may connect to the existing storm sewers so long as the peak rate of discharge does not exceed the amount permitted by § 183-12A of this article.
H. 
Bridges and culverts shall have ample waterway to carry expected flows, based on the following minimum storm frequencies: ten-year for driveways; twenty-five-year for local streets; fifty-year for collector streets; and one-hundred-year for arterials; or as required by the Municipal Engineer. Bridge and/or culvert construction shall be in accordance with the Pennsylvania Department of Transportation specifications.
(1) 
The design criteria contained in this article are intended for use in conjunction with the Chapter 105 Regulations of the Pennsylvania Department of Environmental Protection entitled, “Water Obstructions and Encroachments.” All information and regulations contained in Chapter 105 shall be considered to be incorporated into this article as if reproduced in full.
(2) 
A PA DEP permit in accordance with Chapter 105 shall be required for any obstruction or encroachment in the regulated waters of the commonwealth, prior to the approval of the stormwater plan. All areas of the municipality shall be classified as rural, suburban, or urban, as determined by the Municipal Engineer (See PA DEP § 105.161) for bridge and culvert designs. In the event any question or conflict arises between this article and the PA DEP Chapter 105 Regulations, the design criteria contained in the PA DEP regulations shall govern.
(3) 
Refer to Appendix A, Section II, of this chapter[7] for additional design criteria.
[7]
Editor’s Note: Said appendix is on file and available for inspection in the Loyalsock Township office.
I. 
Detention or retention basins for the management of stormwater peak discharges shall meet the following requirements:
(1) 
Basins shall be installed prior to or concurrent with any earthmoving or land disturbances which they will serve. The phasing of their construction shall be noted in the narrative and on the plan.
(2) 
The design of all facilities over limestone formations shall include measures to prevent groundwater contamination and, where required, sinkhole formation. Soils used for the construction of basins shall have moderate-to-low erodibility factors (i.e., “K” factors of 0.32 or less).
(3) 
Energy dissipators and/or level spreaders shall be installed at points where pipes or drainageways discharge to or from basins. Generally, outlet pipes designed to carry the predevelopment, one-year storm flow will be permitted to discharge to a stream with only an energy dissipator; discharges to drainage swales shall be spread with a level spreader or piped to an acceptable point of discharge downstream.
(4) 
Outlet structures within detention/retention basins shall incorporate childproof, nonclogging trash racks or grates over all horizontally oriented openings. All vertically oriented openings over 12 inches, or larger in any dimension, where entry by a child could cause injury or death, shall be covered with childproof, nonclogging trash racks, except where such openings carry perennial stream flows. Design openings less than six inches in any dimension shall be covered with a pipe screen (e.g., Neenah R-7512 or equivalent). Measures to completely drain detention/retention basins in the event of clogging of the primary design opening(s) shall be incorporated into the design of basin outlet structures. Basin outlet pipes shall have a minimum inside diameter of 15 inches or a cross-sectional area of 176 square inches, except that pipes under a twenty-five foot or greater fill shall not be less than 24 inches or a cross-sectional area of 453 square inches, and shall consist of reinforced concrete.
(5) 
Outlet aprons shall be designed and shall extend at a minimum to the toe of the basin slope. Where spillways will be used to manage peak discharges in excess of the ten-year storm, such spillways shall be constructed to withstand the pressures of impounded waters and convey flows at computed outlet velocities without erosion.
(6) 
Stormwater detention facilities shall be designed to release their total volumes detained within the following maximum time periods:
(a) 
Roofs and parking lots: 24 hours.
(b) 
Detention basin: 48 hours.
(c) 
Infiltration facilities: 72 hours.
(7) 
When the Pennsylvania Department of Environmental Protection requires facilities to be permitted, the designer shall submit all information to the PA DEP regional office, and obtain all necessary approvals and permits pursuant to Pennsylvania Code, Title 25, Chapter 105, Darn Safety and Encroachment Act.
(8) 
Downstream analysis:
(a) 
Where deemed necessary by the Municipal Engineer, the applicant shall submit an analysis of the impacts of detained stormwater flows on downstream areas within the watershed, established with the concurrence of the Municipal Engineer. The analysis shall include hydrologic and hydraulic calculations necessary to determine the impact of peak discharge modifications of the proposed development on critical locations such as dams, tributaries, existing developments, undersized culverts, and floodprone areas.
(b) 
Review and comment on the analysis by the Engineer of a downstream municipality shall be obtained as deemed necessary.
(9) 
Detention basins may be waived by the municipality, upon recommendation of the Municipal Engineer, at sites in close proximity to larger receiving streams, depending on the hydrology of the watershed. This is to facilitate drainage prior to main stream flooding. It shall be incumbent upon the applicant to demonstrate that no downstream increase in stream flooding or channel erosion will result in accordance with § 183-12I(8) of this article, and that no increases in peak discharge within the receiving stream will occur as outlined under § 183-12A of this article.
(10) 
Multiple-use basins. The design and construction of multiple-use stormwater detention facilities are strongly encouraged. In addition to stormwater management, where appropriate, facilities should allow for recreational uses, including ballfields, play areas, picnic grounds, etc. Provision for parking facilities within basins and permanent wet ponds with stormwater management capabilities may also be appropriate. Prior approval and consultation with the municipality are required before design. Multiple-use basins should be constructed so that potentially dangerous conditions are not created.
(11) 
Multiple-development basins. Stormwater management facilities designed to serve more than one property or development in the same watershed are encouraged. Staged construction of existing or proposed multiple-use detention facilities by several developers in conjunction with watershed development is encouraged. Each developer shall be responsible for the incremental increase in stormwater runoff generated by the respective development and incremental construction improvements necessary for the overall detention facility. Prior approval and consultation with the municipality is required before design of such facilities.
(12) 
Alternative detention facilities. Alternative stormwater detention facilities including rooftop, subsurface basins or tanks and in-pipe detention storage, or other approved alternative designs are permitted as determined by the Municipal Engineer.
(13) 
Specific criteria related to the design of detention basins is contained in Appendix A, Section III of this chapter.[8]
[8]
Editor’s Note: Said appendix is on file and available for inspection in the Loyalsock Township office.
J. 
All calculations shall be submitted to the Municipal Engineer on computation sheets for approval. If the Municipal Engineer determines through review and independent computation that the size(s) of storm pipes or detention basins is insufficient, the municipality may require the developer to increase the size(s) of said storm pipes or detention basins. If the storm drainage system design is completed on a computer installation, sufficient supporting data shall be provided to allow comprehensive review by municipal officials.
K. 
When the elevation of any existing or proposed entrance to a structure, including windows, is lower than the elevation of the public cartway serving that site, a grading plan shall be submitted, reviewed and approved as part of the zoning permit process for the proposed structure.
L. 
Natural drainageways shall be utilized to the maximum extent possible in carrying stormwater runoff, provided such use remains consistent with the purpose of this chapter specified in Article I, § 183-3 of this chapter.
M. 
Stormwater management facilities located outside of existing or proposed rights-of-way shall be located within and accessible by easements as follows:
(1) 
Drainage easements.
(a) 
Where a tract is traversed by a watercourse, drainageway, channel or stream, there shall be provided a drainage easement paralleling the line of such watercourse, drainageway, channel or stream. The width of the drainage easement will be adequate to preserve the unimpeded flow of natural drainage in the one-hundred-year floodplain, in accordance with computed top widths for water surface elevations determined under Subsection A of this article.
(b) 
Drainage easements shall provide for maintenance, and for the purpose of widening, deepening, improving or protecting such drainage facilities.
(2) 
Access easements. Where proposed stormwater management facilities are not adjacent to proposed or existing public rights-of-way or are not accessible due to physical constraints, as determined by the Municipal Engineer, a twenty-foot-wide passable access easement specifying rights of entry shall be provided. Access easements shall provide for vehicle ingress and egress on grades of less than 10% for carrying out inspection or maintenance activities.
(3) 
Maintenance easements. A maintenance easement shall be provided which encompasses the stormwater facility and appurtenances and provides for access for maintenance purposes. The maintenance easement must be located at least 20 feet outside of the one-hundred-year surface elevation and the stormwater facility and appurtenances.
(4) 
Easements shall stipulate that no trees, shrubs, structures, excavation, or fill be placed, and no regrading be performed within the area of the easement without written approval from the municipality upon review by the Municipal Engineer. Upon approval of the Municipal Engineer, such landscaping may be placed in maintenance easements, provided it does not impede access.
(5) 
Whenever practicable, easements shall be parallel with and linked to property lines of the subdivision.
(6) 
All easement agreements shall be recorded with a reference to the recorded easement indicated on the site plan. The format and content of the easement agreement shall be reviewed and approved by the Municipal Engineer and Solicitor.
A. 
Stormwater from roadways, parking lots, storm sewers, roof drains, or other concentrated stormwater runoff paths shall not be discharged directly into sinkholes.
B. 
To protect sensitive Karst areas, the Municipal Engineer may require basins to contain an impervious liner. The liner may be of the impervious-membrane type, placed in accordance with the manufacturer’s recommendations, or an approved alternative as approved by the Municipal Engineer.
[Amended 3-22-2005 by Ord. No. 311]
A. 
No regulated earth disturbance activities within the municipality shall commence until approval by the municipality of an erosion and sediment control plan for construction activities.
B. 
An erosion and sediment control plan for construction activities shall be submitted to the municipality for any land developments, nonregulated earth disturbance of 5,000 square feet or more, and regulated earth disturbance activities. DEP has regulations that require an erosion and sediment control plan for any earth disturbance activity of 5,000 square feet or more, under 25 Pa. Code § 102.4(b).
C. 
In addition, under 25 Pa. Code Chapter 92, a DEP “NPDES Construction Activities” permit is required for regulated earth disturbance activities.
D. 
Evidence of any necessary permit(s) for regulated earth disturbance activities from the appropriate DEP regional office or County Conservation District must be provided to the municipality. The issuance of an NPDES Construction Permit [or permit coverage under the statewide General Permit (PAG-2)] satisfies the requirements of Subsection A above.
E. 
A copy of the erosion and sediment control plan and any required permit, as required by DEP regulations, shall be available at the project site at all times.
A. 
Each stormwater management plan shall contain provisions which clearly set forth the ownership and maintenance responsibility of all permanent stormwater management and erosion and sediment control facilities, including:
(1) 
Description of maintenance requirements.
(2) 
Establishment of suitable easements for access to all facilities by public officials, in accordance with Subsection M of this article.
(3) 
Identification of the responsible party or entity for ownership and maintenance of both temporary and permanent stormwater management and erosion and sediment pollution control facilities. In meeting this requirement, the following options are hereby provided for upon approval by the Loyalsock Township:
(a) 
Facilities may be incorporated within individual lots so that the respective lot owners will own and be responsible for maintenance in accordance with recorded deed restriction. A description of the facility or system and the terms of the required maintenance shall be incorporated as part of the deed to the property.
(b) 
Ownership and maintenance may be the responsibility of a property owners’ association. The stated responsibilities of the property owners' association in terms of owning and maintaining the stormwater management facilities shall be submitted with final plans for determination of their approved subdivision plan among the deed records of Lycoming County, Pennsylvania. In addition, the approved subdivision plan and any deed written from said plan for a lot or lots shown herein shall contain a condition that it shall be mandatory for the owner or owners of said lot to be members of said property owners’ association.
(c) 
For stormwater management facilities that are proposed as part of the site development plan, the developer will be required to execute a developer agreement and a maintenance agreement with the municipality for the construction and continued maintenance of the facilities prior to the signature approval on the final plan. Access for inspection by the municipality of all such facilities deemed critical to the public welfare at any reasonable time shall be provided.
(d) 
In the event the above priorities cannot be achieved, or where it is required, the facilities may be dedicated to the municipality in accordance with this chapter. As a condition of municipality acceptance of said facilities, the applicant shall provide 10% of the cost of improvements, in the form of a maintenance bond, as estimated by the applicant’s registered professional, and approved by the Municipal Engineer, to cover contingency maintenance costs for 18 months from the date of stormwater management facilities acceptance of dedication. The ten-percent bond shall be based on the construction costs of the detention basin and outlet structure within the area dedicated to the municipality.
B. 
Operations and maintenance agreement for privately owned stormwater BMPs.
[Added 3-22-2005 by Ord. No. 311]
(1) 
The property owner shall sign an operations and maintenance agreement with the municipality covering all stormwater BMPs that are to be privately owned. The agreement shall be substantially the same as the agreement in Appendix E of this chapter.[1]
[1]
Editor’s Note: Said appendix is on file and available for inspection in the Loyalsock Township office.
(2) 
Other items may be included in the agreement where determined necessary to guarantee the satisfactory operation and maintenance of all permanent stormwater BMPs. The agreement shall be subject to the review and approval of the municipality.
(3) 
All agreements shall be filed at the Lycoming County Courthouse as a separate document. After the agreement is filed, all deeds to the property covered by the agreement must contain a reference to the agreement by record book number, page number, date and where it is filed.
Compliance with the provisions of this chapter shall be in accordance with the following additional general criteria:
A. 
Materials workmanship and methods. All materials, workmanship, and methods of work shall comply with the Pennsylvania Department of Transportation Publication 408 specifications, as accepted and commonly used by the municipality, and shall be considered to be incorporated into this article as if copied in full. In the event a conflict arises between the requirements of this article and the PennDOT Publication 408 specifications, the Municipal Engineer shall resolve the difference, and said opinion shall be binding.
B. 
Record (as-built) drawings. At the completion of the project, and as a prerequisite for the release of the guarantee or issuance of an occupancy permit, the owner(s) or his representative shall:
(1) 
Provide a certification of completion from a registered professional verifying that all permanent facilities have been constructed according to the plans and specifications and approved revisions thereto.
(2) 
Provide a set of approved stormwater management plan drawings showing all approved revisions and elevations and inverts to all manholes, inlets, pipes, and stormwater management facilities.
C. 
The municipality shall inspect stormwater management facilities to ensure proper functioning of such stormwater management facilities. These inspections shall occur at least once annually for five years after the installation of said stormwater management facilities, and then at least once every three years thereafter. The municipality shall also inspect stormwater management facilities after a one-hundred-year-or-greater storm event.
D. 
If the municipality determines at any time that any permanent stormwater management facility has been eliminated, altered, or improperly maintained, the Loyalsock Township shall advise the responsible party of required corrective measures and shall provide said responsible party with a specific time frame to implement the required corrective measures. If such action is not taken by the property owner, the municipality may cause the work to be done and backcharge all costs to the property owners in accordance with Article IV of this chapter.
E. 
Supplemental standards and criteria contained in the technical reference materials listed in Appendix B of this chapter[1] are hereby incorporated into this chapter to govern the hydrologic and hydraulic design provisions contained herein.
[1]
Editor’s Note: Said appendix is on file and available for inspection in the Loyalsock Township office.