On May 5, 2001, the Northbridge Board of Selectmen signed an
Administrative Consent Order (ACO) issued by the Massachusetts Department
of Environmental Protection (DEP). The DEP executed the ACO on May
15, 2001, which is the effective date of the order. The ACO requires
the Town to address certain deficiencies in its sanitary sewer system.
Included among these deficiencies are sources of inflow and infiltration
(I&I) that allow large volumes of ground water to enter into the
sanitary sewer system. The ACO, in conjunction with existing DEP regulations,
outlines procedures to be followed for obtaining a permit for extensions
to the sewer collection system of the Town of Northbridge. This policy
is intended to clarify and summarize the requirements to obtain a
sewer extension permit.
The following documents, containing guidance and direction relative
to the extension of sanitary sewers in the Town of Northbridge, are
incorporated into this policy by reference.
1. 314 CMR 7.00 SEWER SYSTEM EXTENSION AND CONNECTION PERMIT PROGRAM
2. MGL c.
21, § 43. Permit proceedings and determinations; regulations;
necessity and requirements of permit; application; forms; fees.
3. Administrative
Consent Order (ACO) and Notice of Noncompliance, File Number ACO-CE-01-1010
dated 5/15/01 and issued by the Commonwealth of Massachusetts, Executive
Office of Environmental Affairs, Department of Environmental Protection
4. Town of
Northbridge, Massachusetts, Inflow and Infiltration Reduction Program
Sewer Connection Policy (I&I Policy), Current Edition
No person shall construct, effect, maintain, modify or use any
sewer system extension or connection without a currently valid permit
from the Director of the Massachusetts Department of Environmental
Protection pursuant to MGL c. 21, § 43 and 314 CMR 7.00,
unless exempted in 314 CMR 7.05. Exemptions under this provision must
be fully documented by the project proponent in writing to the Town.
Any person who proposes to construct, effect, maintain, modify or
use a sewer system extension or connection must obtain a permit by
filing the application form in accordance with 314 CMR 7.00 and 2.00.
Permit applications shall be prepared by the person proposing the
extension or connection or their representative.
The application, in three copies, shall be submitted for review,
complete with all supporting information to the Northbridge Department
of Public Works (DPW), prior to requesting the approval of the Town.
The DPW shall annotate on the application such special conditions
as may be deemed necessary to insure the application is in compliance
with DEP regulations and the requirements of the above referenced
documents. The application then shall be submitted to the Northbridge
Board of Selectmen for review and approval. The Board of Selectmen
may require the project proponent to make such presentations and/or
provide such additional information as it may determine necessary
to properly evaluate the application. Upon majority vote of the Board
of Selectmen to approve the application, the Chairperson shall sign
the application recommending approval. The project proponent may then
transmit the signed application to the DEP for review and final approval.
The normal processing time for review and approval of applications
will be two to four weeks from receipt of the application. In the
event that additional information is required to fully evaluate the
application, the processing time will be extended accordingly until
all issues have been resolved. The project proponent shall provide
the Northbridge DPW with copies of all correspondence to and from
the DEP on all matters relative to the application after submission.
The following are some, but not necessarily all, of the special
conditions that may be applied to permit applications:
1. No connection or extension will be permitted if it will introduce
new flow into an existing sewer system component that has been listed
in the ACO as a Deficient System Component. As identified Deficient
System Components are upgraded and they are removed by the DEP from
the list of Deficient System Components the restriction on new connections
will be removed.
2. For every
one gallon of new flow introduced into the sewer system there must
be a reduction of four gallons of excess inflow and infiltration in
the system. The project proponent must fully comply with the terms
of the above reference I&I Policy.
3. No sewer
connection permit shall be issued for any individual connection if
there are not sufficient I&I reduction credits available in the
Town of Northbridge "Sewer Bank" to meet the 4:1 I&I reduction
requirement of the ACO. The Board of Selectmen will impose a moratorium
on all new connections that are governed by the ACO if the issuance
of such a connection permit would result in a violation of the ACO
or any other applicable regulation. Authority to initiate such a moratorium
is delegated to the Town Manager subject to ratification by vote of
the board.
Applications for sewer extensions shall be accompanied by a
processing fee of not less than $25 nor more than $250. The fee shall
be based upon the total estimated daily flow in gallons per day (gpd)
times $0.10. Fee shall be by check made payable to "Northbridge Sewer
Enterprise Fund". All fees collected shall be deposited into the I&I
contribution account.
This policy shall become effective on the date adopted by the
Northbridge Board of Selectmen.
[Adopted 6-18-2007; effective 7-1-2007]
A connection fee for a new service connection to Residential,
Commercial or Industrial premises will be charged by the Northbridge
Sewer System at the time application is made for service, as follows:
Type of Connection
|
Fee
|
---|
Existing single-family residence
|
$924.00
|
Existing multifamily residence (first unit)
|
$924.00
|
Each additional existing unit
|
$528.00
|
New single-family residence
|
$7,920.00
|
New multifamily residence (first unit)
|
$7,920.00
|
Each additional unit
|
$6,600.00
|
Commercial or Industrial (minimum)
|
$9,240.00
|
Commercial or Industrial (whichever is greater)
|
$462.00 per fixture
|
Whenever a commercial or industrial premises is served by more
than one connection to the Town's mains, the connection fee schedule
above shall apply to each connection. The total number of fixtures
will not be added together to determine the connection fee.