Inspection of guaranteed improvements. The guaranteed improvements
shall not be deemed completed until the Village Engineer, or the Village's
appointed inspector, has inspected the guaranteed improvements, determined
that the approved engineering plans have been satisfactorily implemented,
and has issued a written declaration of completion to the applicant.
Upon written request from the applicant, and promptly thereafter,
at a time mutually agreeable to the applicant and the Village Engineer
or its appointed inspector, the Village Engineer or its appointed
inspector shall inspect the guaranteed improvements and report its
findings as to acceptability and completeness to the applicant. The
Village Engineer shall prepare a punch list of items, if any, to be
performed or corrected and shall fix a time within which the applicant
shall perform or correct the items listed thereon. Following the applicant's
performance or correction of the items on the punch list, the Village
Engineer or its appointed inspector shall make another review of the
guaranteed improvements, and shall either issue a written declaration
declaring the guaranteed improvements to be complete, or present another
punch list to the applicant.