The following supplemental use standards apply to the permitted uses listed in Table §
61-9 above and shall apply when the permitted use is allowed in the underlying zoning district.
Water-dependent research facilities or activities operated by
state, federal, or local agencies or educational institutions may
be permitted in the Buffer, if non-water-dependent structures or facilities
associated with these projects are, to the extent possible, located
outside of the Buffer.
Commercial water-dependent fisheries, including, but not limited
to, structures for crab shedding, fish off-loading docks, shellfish
culture operations and shore-based facilities necessary for aquaculture
operations and fisheries activities may be permitted in the Buffer
in Intensely Developed Areas, Limited Development Areas and Resource
Conservation Areas.
Except as provided in Subsections A, B and C below, construction
of a dwelling unit or other non-water-dependent structure on a pier
located on state or private tidal wetlands within the Critical Area
is prohibited.
A. A building permit for a project involving the construction of a dwelling
unit or other non-water-dependent structure on a pier located on state
or private wetlands within the Critical Area may be approved, provided
a permit was issued by the Department of Natural Resources on or before
January 1, 1989.
B. A building permit for a project involving the construction of a dwelling
unit or other non-water-dependent structure on a pier located on state
or private wetlands within the Critical Area may be approved if the
following conditions exist:
(1) The project is constructed on a pier that existed as of December
1, 1985, that can be verified by a Department of Natural Resources
aerial photograph dated 1985, accompanied by a map of the area;
(2) The project does not require an expansion of the pier greater than
25% of the area of piers or dry docks removed on the same property;
however, additional expansion may be allowed in the amount of 10%
of the water coverage eliminated by removing complete piers from the
same or other properties. If the horizontal surface of a pier to be
removed is not intact, but pilings identify its previous size, then
that area may be used in determining the additional expansion permitted.
The project expansion based on water coverage eliminated can be considered
only if all nonfunctional piers on the property are removed except
for the project pier. The total expansion may not exceed 35% of the
original size of the piers and dry docks removed; and
(3) The project is located in an Intensely Developed Area.
C. A building permit for the repair of an existing dwelling unit or
other non-water-dependent structure on a pier located on state or
private wetlands within the Critical Area may be approved.
D. If a structure that is not water dependent is permitted under the
exceptions included in this section, an applicant is required to demonstrate
that the project will meet the following environmental objectives
using the standards established herein:
(1) The construction and operation of the project will not have a long-term
adverse effect on the water quality of the adjacent body of water;
(2) The quality of stormwater runoff from the project will be improved;
and
(3) Sewer lines or other utility lines extended for the pier will not
affect the water quality of adjoining waters.
A golf course, excluding main buildings and/or structures such
as the clubhouse, pro-shop, parking lot, etc., may be permitted in
Resource Conservation Areas, provided:
A. Such use is permitted in the underlying zoning; and
B. Development is in accordance with the official guidance adopted by
the Critical Area Commission on August 3, 2005.
Nonmaritime heavy industry may be permitted if:
A. The site is located in an Intensely Developed Area; and
B. The activity or facility has demonstrated to all appropriate local
and state permitting agencies that there will be a net improvement
in water quality to the adjacent body of water.