Any regulated activity that meets the following exemption criteria
is exempt from the part(s) of this chapter as specified herein. However,
the requirements of this chapter shall otherwise remain in effect.
The criteria for exemption in this section apply to the total development
proposed, including instances in which the development is proposed
to take place in phases. The date of enactment of this chapter shall
be the starting point from which future development and the respective
proposed impervious surface computations shall be cumulatively considered
and regulated. Exemption shall not relieve an applicant from implementing
such measures as necessary to meet the intent of this chapter, or
compliance with any NPDES permit requirements.
A. Regulated activities that create DIAs equal to or less than 1,000
square feet are exempt from the peak rate control and the SWM site
plan preparation requirements of this chapter.
B. Regulated activities that create DIAs greater than 1,000 square feet
and equal to or less than 5,000 square feet are exempt only from the
peak rate control requirement of this chapter.
C. Agricultural activity is exempt from the rate control and SWM site
plan preparation requirements of this chapter provided the activities
are performed according to the requirements of 25 Pa. Code Chapter
102.
D. Forest management and timber operations are exempt from the rate
control and SWM site plan preparation requirements of this chapter
provided the activities are performed according to the requirements
of 25 PA Code Chapter 102.
E. The use of land for domestic (i.e., for a single individual dwelling
unit) gardening and landscaping is exempt from specific approval and
permitting under this chapter so long as such activities comply with
all other applicable ordinances and statutes.
F. Exemptions from certain provisions of this chapter shall not relieve the applicant from the requirements in §
268-10D through
L of this chapter.
G. The Township may deny or revoke any exemption pursuant to this section
at any time for any project that the Township determines poses a threat
to public health, safety, property or the environment.
The low-impact development practices provided in the BMP Manual
shall be utilized for all regulated activities to the maximum extent
practicable. Water volume controls shall be implemented using the
Design Storm Method in Subsection A or the Simplified Method in Subsection
B below. For regulated activity areas equal or less than one acre
that do not require hydrologic routing to design the stormwater facilities,
this chapter establishes no preference for either methodology; therefore,
the applicant may select either methodology on the basis of economic
considerations, the intrinsic limitations on applicability of the
analytical procedures associated with each methodology, and other
factors.
A. The Design Storm Method (CG-1 in the BMP Manual) is applicable to
any size of regulated activity. This method requires detailed modeling
based on site conditions.
(1) There shall be no increase in the post-development total runoff volume
for all storms equal to or less than the two-year twenty-four-hour
duration precipitation.
(2) For modeling purposes:
(a)
Existing (predevelopment) nonforested pervious areas must be
considered meadow.
(b)
Twenty percent of the existing impervious area of a project
site, when present, shall be considered meadow in the model for existing
conditions.
B. The Simplified Method (CG-2 in the BMP Manual) provided below is
independent of site conditions and should be used if the Design Storm
Method is not followed. This method is not applicable to regulated
activities greater than one acre or for projects that require design
of stormwater storage facilities.
(1) For new impervious surfaces.
(a)
Stormwater facilities shall capture at least the first two inches
of runoff from all new impervious surfaces.
(b)
At least the first one inch of runoff from new impervious surfaces
shall be permanently removed from the runoff flow, i.e., it shall
not be released into the surface waters of the commonwealth. Removal
options include reuse, evaporation, transpiration, and infiltration.
(c)
Wherever possible, infiltration facilities should be designed
to accommodate infiltration of the entire permanently removed runoff;
however, in all cases at least the first 0.5 inch of the permanently
removed runoff shall be infiltrated.
(d)
This method is exempt from the requirements of §
268-13, Rate controls.