A. 
All regulated activities shall be conducted, operated and maintained in accordance with the requirements set forth in Articles III, VII, and VIII of this chapter. When a SWM site plan is required by this chapter, all regulated activities shall be performed in accordance with the requirements of the final approved SWM site plan.
B. 
The Township Engineer or other Township designee shall be provided access to the site to inspect all phases of the erosion and sediment control measures and installation of the permanent BMPs and conveyances at such times as deemed appropriate by the Township Engineer or other Township designee.
[Amended 12-15-2014 by Ord. No. 424-14]
C. 
Periodic inspections may be made by the Township Engineer or other designee during construction. The final approved SWM site plan shall be on file and available for viewing at the site throughout the duration of the construction activity.
[Amended 12-15-2014 by Ord. No. 424-14]
D. 
Inspections, including but not limited to a final inspection, of all constructed BMPs, conveyances, or other stormwater facilities and related improvements may be conducted by the Township Engineer or other designee to confirm compliance with this chapter and with the final approved SWM site plan prior to the issuance of any occupancy permit, use permit, or other form of final approval of the project by the Township.
[Amended 12-15-2014 by Ord. No. 424-14]
E. 
Upon completion of construction, every permanent stormwater BMP, conveyance or other stormwater management facility constructed or used as part of the regulated activity shall be operated, maintained and inspected by the landowner, or other designated person, in accordance with the O&M plan and O&M agreement approved by the Township.
[Amended 12-15-2014 by Ord. No. 424-14; 10-17-2022 by Ord. No. 452-22]
F. 
The Township or its designee may periodically inspect any permanent stormwater BMP, conveyance or stormwater management facility for compliance with this chapter, an approved O&M plan, or an approved O&M agreement, per the provisions of Article IX. The Township may inspect at any time it has reason to believe a violation exists. The Township may pursue enforcement for violations consistent with the provisions of Article IX.
[Amended 12-15-2014 by Ord. No. 424-14; 10-17-2022 by Ord. No. 452-22]
G. 
If an NPDES permit for stormwater discharges associated with construction activities was required for the regulated activity, a notice of termination (NOT) approval must be obtained upon completion of construction prior to final approval of the project by the Township.
[Added 10-17-2022 by Ord. No. 452-22]
A. 
For all regulated activities, the applicant shall provide to the Township final as-built plans (signed and sealed by a qualified licensed professional) of all BMPs, conveyances, other stormwater facilities, and related improvements shown in the final approved SWM site plan.
[Amended 12-15-2014 by Ord. No. 424-14]
B. 
The final as-built plans shall include the following for all BMPs, conveyances, other stormwater facilities and related improvements:
(1) 
The location, elevations, dimensions, and as-built conditions of all BMPs, conveyances, other stormwater facilities, and related improvements, including topographic contours and all typical details for storm drainage and conveyance systems, stormwater management facilities and impervious surfaces (including an impervious surfaces table that identifies preexisting, as-approved and as-built impervious surface areas) included in the approved SWM site plan. The latitude and longitude coordinates for all permanent SWM BMPs must also be submitted at the central location of the BMPs; and
[Added 10-17-2022 by Ord. No. 452-22]
(2) 
Explanation of any discrepancies or variations from the final approved SWM site plan, other related approved construction plans, calculations and specifications (and approved revisions thereto).
C. 
The final as-built plans shall include a certification of completion signed and sealed by a qualified licensed professional verifying that all permanent BMPs and conveyances have been constructed according to the final approved SWM site plan and related approved construction plans, calculations and specifications.
D. 
All areas of the regulated activity draining to BMPs must be stabilized prior to submittal of the as-built plans.
E. 
After receipt of the as-built plans by the Township, the Township or its designee may review the as-built plans for consistency with this chapter, the final approved SWM site plan, other related approved construction plans, and subsequent approved revisions thereto, as well as actual conditions at the site, and the Township may conduct a final inspection, as per § 388-30D.
[Amended 12-15-2014 by Ord. No. 424-14]
F. 
The as-built plans must be received by the Township within 90 days from substantial completion of the work, reviewed and determined to be acceptable by the Township Engineer prior to:
[Amended 12-15-2014 by Ord. No. 424-14]
(1) 
Close out of the drainage permit or other close out of the project by the Township;
(2) 
Release of the financial security or other performance guarantee; and
(3) 
Dedication of the stormwater facilities to the Township, or conveyance to a homeowners' association, or other person responsible for operation, maintenance and repair.
G. 
Final occupancy permit(s) or use permit or other final approval to use or operate the constructed improvement may not be issued by the Township until the final as-built plans have been accepted by the Township Engineer.
[Amended 12-15-2014 by Ord. No. 424-14]
H. 
Upon final acceptance of the final as-built plans by the Township Engineer, the applicant shall review and, if required by the Township, revise and re-record the O&M plan and the O&M agreement to reflect the final as-built conditions and information for each permanent BMP or conveyance, in accordance with the requirements of Article VII.
[Amended 12-15-2014 by Ord. No. 424-14]
I. 
All or portions of the final as-built plans shall be recorded if required by the Township.
[Amended 12-15-2014 by Ord. No. 424-14]