[Ord. No. 2010-1621 §1, 4-20-2010]
The applicant must notify the City before the commencement of
construction. In addition, the applicant must notify the City in advance
of construction of critical components of the stormwater practices
on the approved stormwater management design plan, as determined by
the City. The City may, at its discretion, issue verbal or written
authorization to proceed with critical construction steps, such as
installation of permanent stormwater practices based on stabilization
of the drainage area and other factors.
[Ord. No. 2010-1621 §1, 4-20-2010]
The City or its representatives shall conduct periodic inspections
of the stormwater practices shown on the approved stormwater management
design plan, and especially during critical installation and stabilization
steps. All inspections shall be documented in writing. The inspection
shall document any variations or discrepancies from the approved plan,
and the resolution of such issues. Additional information regarding
inspections can be found in the Stormwater Design Manual. A final
inspection by the stormwater authority is required before any performance
bond or guarantee, or portion thereof, shall be released.
[Ord. No. 2010-1621 §1, 4-20-2010]
If a stormwater BMP is found to be inadequate by virtue of physical
evidence of operational failure, even though it was built as called
for in the approved stormwater management design plan, it shall be
corrected by the applicant before the certificate of completion is
issued. If the applicant fails to act, the City may use the performance
bond or guarantee to complete the work.
[Ord. No. 2010-1621 §1, 4-20-2010]
Subsequent to final installation and stabilization of all stormwater
BMPs shown on the stormwater management design plan, submission of
all necessary as-built plans, and final inspection and approval by
the City, the City shall issue a stormwater certificate of completion
for the project. In issuing such a certificate, the City shall determine
that all work has been satisfactorily completed in conformance with
this Chapter.