As used in this article, the following terms shall have the
meanings indicated:
CAPITAL IMPROVEMENT
Includes preliminary engineering, engineering design studies,
land surveys, right-of-way acquisition, engineering, permitting and
construction of all the necessary features for increasing the capacity
of the sewage treatment plant, including, but not limited to:
A.
Construction of sewer laterals.
B.
Construction of pumping stations.
C.
Construction of gravity lines.
D.
Switching the operations mode of said plant from extended aeration
to contact stabilization.
E.
Construction of sewer lines.
EXPANSION
A change in the operational mode of said plant from extended
aeration to contact stabilization.
FEE PAYER
A person commencing a land development activity which generates
domestic sewage discharge from a residential or commercial dwelling
and which requires the issuance of a building permit from that municipality
in which the real property is located.
SITE-RELATED IMPROVEMENTS
Capital improvements for direct access improvements to the
development in question. Direct access improvements include, but are
not limited to, the following:
A.
Construction of sewer laterals.
B.
Construction of sewer lines.
C.
Construction of gravity lines.
[Amended 10-27-1997 by L.L. No. 6-1997]
The amount of the fee may be determined as follows: The fees
will be in a reasonable amount to be determined by the Board of Trustees
of the Village after additional input by the Rensselaer County Water
and Sewer Authority or other appropriate entity.