The improvements set forth in this article shall be required in all developments, and shall be in addition to all other requirements established in this chapter, other applicable laws, ordinances or regulations and those imposed as conditions upon plan approval. All such required improvements shall be constructed and/or implemented by the date(s) set in the developer's agreement for their completion. If not constructed with completion accepted by the Township prior to release of the approved final plan for recording, the developer shall tender to the Township financial security to ensure completion of such improvements, which shall be tendered and held in accordance with provisions of Article
V of this chapter.
A. Required improvements shall be constructed in accordance with design standards, criteria, specifications and construction standards as set forth in this chapter, Chapter
116, Stormwater Management, Chapter
29, Part
2, Public and Private Improvements, and other applicable laws, ordinances and regulations, as are then in effect, and with conditions on plan approval.
B. Failure or refusal by developer to construct and complete all required
improvements in accordance with applicable specifications by the date(s)
set for their completion in this chapter or the developer's agreement
shall constitute a violation of this chapter and a default by the
developer under the developer's agreement, and shall entitle
the Board of Supervisors to exercise the Township's rights against
financial security in order to effect completion of all required improvements.
C. The Board of Supervisors, upon request therefor and good cause shown,
shall have discretion to grant or deny extension of time for completion
of required improvements. The Board of Supervisors shall not be obligated
to allow extension where good cause for delay is not found to exist,
and the grant of one extension shall not obligate the Board to allow
additional extensions.
D. Criteria, design and construction standards for improvements as set forth in Chapter
116, Stormwater Management, and Chapter
29, Part
2, Public and Private Improvements, are incorporated in this chapter by reference and, as may in the future be amended, shall constitute, together with other regulations of this or any other applicable ordinance, the standards for construction of such improvements.
E. Wherever standards for required improvements are not set forth in this chapter, Chapter
116, Stormwater Management, or Chapter
29, Part
2, Public and Private Improvements, the applicable standards, specifications and requirements of PennDOT shall govern.
F. All work must be open and available for inspections as required in Chapter
29, Part
2, Public and Private Improvements. The Township will not accept completion of improvements unless all required inspections have been made.
Minimum use driveways shall be constructed in accordance with the standards in §
29-44, Driveways, of Chapter
29, Code Enforcement, Part
2, Public and Private Improvements.