[R.O. 2003 §405.270; Ord. No. 734 §3, 7-7-2005]
A. Any person, firm, partnership, corporation, association, co-partnership or trust, prior to commencing any private work on public works projects in the City of Buckner, Missouri, shall comply with Sections
400.450 and
402.090, where relevant, and the following regulations and provisions:
1.
Plans and specifications for the private construction of public works projects including, but not limited to, streets, sidewalks, drainage systems, water distribution system, sewers or thoroughfares to be dedicated to and maintained by the City of Buckner, shall be submitted to the Board of Aldermen for approval. These plans will be submitted at the different City approval stages, which include: a preapplication review; an application to request an amendment to the City Plan as specified in
Schedule 1 of this Chapter
405; a preliminary (conceptual) plat; approval of design per phase/final engineering (construction) drawings; final plat; general construction permit per phase; final inspection and acceptance of infrastructure per phase; building permits for individual lots.
Schedule 1 of this Chapter has additional information on the requirements at each stage.
2.
When construction design is complete, the City shall be provided
with plans marked as reviewed by the City's Engineer. The developer
and his contractors shall only build from plans that have been annotated
as having been approved, signed and dated by the City Engineer to
include change orders. No construction shall start until the City
Engineer has approved all associated plans. The developer shall submit
as-built plans when construction is complete.
3.
The developer shall obtain a general construction permit from the office of the City Clerk authorizing the construction mentioned and set forth in the approved plans and specifications submitted. A permit will be issued for each phase of the development and includes all inspections, to include the final, associated with the work of the general contractor and subcontractors involved in building the infrastructure of the subdivision (see
Schedule 2 of this Chapter). Work for which the permit is issued shall be started within one (1) year of issuance; if work has not started by this time, a new permit shall be required [this means that the process shall be started again as per Subsection
(A)(1) and
(2) of this Section]. An additional condition of issuing the permit shall be that the developer agrees to give companies the City has franchise agreements with "access to open trenches for deployment of their respective facilities and written notice of the date of availability of trenches. The developer shall be responsible for the digging and backfilling of all trenches. The franchising company shall be responsible for engineering and deployment of labor applicable to its facilities." These requirements are per the City's franchise agreements. To issue the permit, the City requires:
a.
Copies of all State permits, which include the following:
(1) Land disturbance permit, MoDNR;
(2) Water line permit, MoDNR;
(3) Sewer line permit, MoDNR;
(4) Street connection to State highway and MoDOT permits
when necessary; and
(5) Any other necessary permits.
b.
The developer shall provide proof of insurance against all liability
and name the City as an additional insured.
c.
The developer shall provide the City with a performance and maintenance bond subject to the requirements of Subsection
(A)(7) and
(8).
4.
No general construction permit shall be issued by the City of Buckner unless the applicant shall pay the City Clerk a fee based upon the structure set in
Schedule 2 of this Chapter.
5.
Following the issuance of the permit provided for herein, construction
shall not be started until:
a.
The Building Official has been notified as to the time, location
and scope of the construction by the developer.
b.
A meeting between the developer, general contractor, subcontractors,
the Mayor, City Administrator, Building Official, City Engineer and
others required by the City Administrator has been held.
6.
Prior to the start of soildisturbing activities, soil testing
may be done, at the City's expense, to determine a baseline for
moisture and compaction. Dirt removed from trenches and roadbed surfaces
that is not capable of being compacted, in accordance with the specifications
set out in the Standard Specifications and Design Criteria of the
American Public Works Association (APWA), shall not be used as backfill.
7.
No construction shall be accomplished and the permit provided
for herein shall not be issued until one (1) of the following two
(2) options is selected by the developer and approved by the Board
of Aldermen:
a.
The developer shall provide to the City Clerk a dual obligee
performance bond in an amount equal to the cost of construction and
satisfactory to the City Attorney guaranteeing the complete performance
of the contemplated construction for which the permit herein provided
for is issued and further guaranteeing and insuring that such construction
shall be accomplished in a workmanlike manner, as well as and further
protecting the City of Buckner, Missouri, and insuring said City from
any loss or damage. If the performance bond is obtained, the City
will record the final plat within thirty (30) days of approval by
the Board of Aldermen.
b.
If a performance bond is not posted, then the final plat drawings shall be held at City Hall until seventy percent (70%) of the phase is completed and accepted, as per the City's subdivision acceptance procedures in Section
405.280, and shall then be recorded at Jackson County.
8.
Upon completion of construction and acceptance by the Board
of Aldermen for which the permit herein provided is issued, the developer
shall provide a dual obligee maintenance bond in an amount equal to
the total cost of construction guaranteeing against defects in construction
of storm sewers, sanitary sewers and water lines for a period of two
(2) years and guaranteeing against defects in the construction of
streets (includes curbs and sidewalks) for a period of two (2) years,
as well as and further protecting the City of Buckner, Missouri, and
insuring said City from any loss or damage. The period for the maintenance
bond shall not be construed as starting until the Board of Aldermen
vote to accept the subdivision or phase as being one hundred percent
(100%) completed.
9.
All construction work may be stopped at any time by the City
Administrator, City Engineer or their agent when, in the opinion of
the City Engineer or Building Official, the workmanship, materials
used or procedures of work do not meet the requirements or comply
with the City codes, ordinances, specifications and procedures for
such work.
10.
If changes have to be made that impact easements, written consent
shall be obtained from the City Administrator or City Engineer. Upon
their approval, the developer shall have a "mini-plat" recorded at
Jackson County. A mini-plat consists of at least one (1) to three
(3) representative lots, instead of all lots, with reference to all
other impacted lots, showing the relevant easements.
11.
All work, accomplished by means of a permit issued under this Chapter, shall be subject to final inspection for City maintenance by the City Engineer and Building Official in accordance with Section
405.280 and their recommendations shall be made to and action taken thereon by the Board of Aldermen and Mayor.
12.
Any lot within the City of Buckner or any addition thereof in accordance with Sections
400.480 and
402.100 of the Buckner Municipal Code and Section 445.070, RSMo., may not be sold prior to:
a.
The plat thereof being made out, which includes a title search
and a professional survey conducted;
b.
Acknowledgment of said plat by the Board of Aldermen; and
c.
The recording of said plat at the Jackson County Recorder of
Deeds.
13.
Building permits for individual lots may be issued only after
the following conditions are satisfied:
a.
The recording of the final plat at Jackson County.
b.
Acceptance by the City of the infrastructure as per subdivision acceptance procedures in Section
405.280.
14.
Final approval of building permits or occupancy permits may
only be issued by the Building Inspector after verifying with the
Building Official that all water taps, sewer taps, driveways and sidewalks
have been installed according to the City ordinances.
15.
The as-built drawings for the phase shall be submitted to the
City prior to the City accepting one hundred percent (100%) of the
infrastructure.
[R.O. 2003 §405.280; Ord. No. 734 §3, 7-7-2005]
A. When the developer determines he is nearing seventy percent (70%)
completion of construction, he shall request a verification of progress
from the Building Official.
B. The Building Official shall request a construction status report
from the City's Construction Inspector. The City Engineer will
specify the percentage of construction completion for the phase.
C. The Building Official shall make a written recommendation to the
Board of Aldermen on whether the phase is ready to enter the acceptance
process based upon the reports from the City Inspector and City Engineer.
D. The Board of Aldermen shall review the reports and recommendations
mentioned above and determine if all requirements of the City's
ordinances have been met.
E. If the Board of Aldermen determines that there are elements of the
City ordinances that have not been met or that some aspects of construction
do not meet APWA code or other agreed upon specifications, they will
direct the Building Official to provide a detailed report of the Board's
"Refusal to Authorize Starting the Acceptance Procedures" to the developer.
The report shall specifically state what shall be corrected before
the City will authorize the recording of the final plat.
F. When the Board of Aldermen determine that the final plat is ready
to be recorded at Jackson County, they shall direct the City Clerk
to obtain the necessary signatures on the final plat and to then record
said plat at the Jackson County Recorder of Deeds.
G. If seventy percent (70%) or beyond of the infrastructure of the phase
has been completed and accepted by the Board of Aldermen and the developer
is agreeable to posting a dual obligee bond equal to the remaining
percentage of uncompleted work, then building permits for lots may
be issued provided the final plat has been duly recorded.
[R.O. 2003 §405.290; Ord. No. 734 §3, 7-7-2005]
A. Minimum standards for street construction and storm drainage for
the City of Buckner are as follows:
1.
Curb And Gutter. All curb and gutter shall
be twenty-four (24) inches wide, Portland cement concrete and constructed
as specified in Section 2209, APWA Street Specifications and Standards,
latest edition. Integral curb and gutter shall be used in Portland
cement concrete. (Section 2208, APWA Street Specifications and Standards
latest edition)
2.
Base Course And Surface.
a.
Class I Street (Arterial) shall be a minimum of forty (40) feet
wide, back to back of upright curb and shall be constructed of asphaltic
concrete a minimum of ten (10) inches total with an eight-inch compacted
asphaltic concrete base and a two-inch compacted asphaltic concrete
surface (Section 2205, APWA Street Specifications, latest edition).
Alternate: eight (8) inches of Portland cement concrete with integral
curbs (Section 2208, APWA Street Specifications, latest edition).
Minimum seventy (70) feet R/W.
b.
Class II Street (Collector) shall be a minimum of thirty-six
(36) feet wide, back to back of upright curb and constructed of asphaltic
concrete a minimum of nine (9) inches total with a seven-inch compacted
asphaltic concrete base and a two-inch compacted asphaltic concrete
surface. Alternate: six (6) inches Portland cement concrete with integral
curb and gutter (Section 2203, APWA Street Specifications and Standards,
latest edition). Minimum sixty (60) foot R/W.
c.
Class III Street (Residential) shall be a minimum of twenty-eight
(28) feet wide, back to back of rollback curb and constructed of asphaltic
concrete a minimum of eight (8) inches total with six-inch compacted
asphaltic concrete base and a two-inch compacted asphaltic concrete
surface (Section 2205, APWA Street Specifications, latest edition).
Alternate: six (6) inches of Portland cement concrete with integral
curb and gutter (Section 2208, APWA Street Specifications, latest
edition). Minimum right-of-way of fifty (50) feet.
3.
Grading And Subgrade Preparation.
a.
Grading shall be done in accordance with Section 2102, APWA
Street Specifications, latest edition.
b.
Subgrade preparation shall be done in accordance with Section
2200, APWA Street Specifications, latest edition.
[R.O. 2003 §405.300; Ord. No. 734 §3, 7-7-2005]
A. The standard specifications for the City of Buckner, Missouri, on
all water lines in subdivisions shall be such specifications as set
out by the Missouri Department of Natural Resources and those set
in the Standard Specifications and Design Criteria of the American
Public Works Association (APWA).
1.
Type Of Material. All water mains shall be
C900AWWA plastic pipe.
2.
Fire Hydrants. All fire hydrants shall be a
WB67 Pacer brand and shall be on a six-inch water line three hundred
fifty (350) feet apart (Reference: MDNR Design Guides for Community
Water Systems 8/29/03). All new subdivisions must provide a minimum
of one (1) shutoff wrench for every three (3) hydrants (or any number
under three (3)).
3.
Location Wire. Location wire shall be installed
along all water line pipes for detection purposes. The location wire
shall be No. 9 wire with a blue coating and laid ten (10) inches above
the pipe on top of the aggregate embedment. In addition, the location
wire shall be connected to valve boxes and existing iron piping in
the same manner. Any splices to the wire shall be done with a APWA
approved kit.
4.
Embedment Of Pipe. All water lines shall be embedded in three-eighths-inch buckshot aggregate to ten (10) inches above the pipe; see APWA Section 2901 and
Schedule 7 at the end of this Chapter.
[R.O. 2003 §405.310; Ord. No. 734 §3, 7-7-2005]
A. The standard specifications for the City of Buckner, Missouri, on
all sanitary sewers in subdivisions shall be such specifications as
set out by the Missouri Department of Natural Resources and those
set in the Standard Specifications and Design Criteria of the American
Public Works Association (APWA).
B. Location. No manhole shall be located in an area
where a sidewalk will be constructed or in the paved area of a street.
C. Manhole Elevations. The grade shall be one-half
(1/2) inch per foot for the first eleven (11) feet, except the sidewalk
area, which shall be one-fourth (1/4) inch per foot to the top edge
of the back of the curb.
D. Backflow Prevention Device. A backflow prevention
shall be required on all new sanitary sewer connections and recommended
on all old sewer connections.
E. Embedment Of Pipe. All sanitary sewer lines shall be embedded in No. 4 or No. 8 aggregate to ten (10) inches above the pipe; see APWA Section 2503.3 and
Schedule 8 at the end of this Chapter.
[R.O. 2003 §405.320; Ord. No. 734 §3, 7-7-2005]
A. All design and construction of storm sewers and appurtenances shall
conform to APWA Storm Sewer Specifications, latest edition.
1.
Reinforced Concrete Pipe. Reinforced concrete
pipe (RCP) is required under all roadbeds.
2.
High-Density Polyethylene Pipe (HDPE). HDPE
pipe is allowed otherwise but only if one-hundred-percent construction
observation is provided.
3.
Catch Basins. All catch basins, lids must have
a galvanized or better trash guard.
4.
Embedment Of Pipe. All storm sewer lines shall
be embedded in crushed rock or pea gravel with not less than ninety-five
percent (95%) passing three-quarter-inch (ninety-five percent (95%)
passing one (1) inch for thirty-inch pipe and larger) and not less
than ninety-five percent (95%) retained on three-eighths (3/8) inch
to be placed in not more than six-inch layers or lifts and compacted
by slicing with a shovel or vibrating.
[R.O. 2003 §405.330; Ord. No. 734 §3, 7-7-2005]
A. Detention basins in the City shall be built according to the following
guidelines:
1.
The drainage swale in the middle of the basin shall have a ten-foot-wide
ribbon of concrete in a "V" shape its entire length.
2.
There shall be a six-inch-deep base of one-inch aggregate under
the concrete ribbon.
3.
Toe walls shall be installed for all inflow and outflow pipes
and for all restriction walls.
4.
All riprap shall have a filter blanket under it as per Section
2605.3 D of the APWA standards.
5.
Any area requiring riprap must be grouted in concrete as per
Section 2605.2-3 of the APWA standards.
[R.O. 2003 §405.340; Ord. No. 734 §3, 7-7-2005]
All paved streets, water lines, sanitary sewer and storm sewer
lines shall be extended up to the adjoining property at a location
directed by the City Engineer so that when said adjoining property
is subdivided, the adjoining property being subdivided can join the
previously laid street, water lines, sanitary sewer and storm sewer
lines with its streets, water lines, sanitary sewer and storm sewer
lines.