A.
It is the intent that no street or way through private property shall be accepted by the Town unless the same be previously constructed and completed in accordance with the approved definitive subdivision plan and the following specifications. All work done under this section shall be done under the direction of the Planning Board. No aforementioned bond or covenant shall be released until full approval in writing of all work done under this section is received by the Planning Board from the Planning Board agent. The following minimum specifications shall govern the installation of all roadways, utilities and other improvements in all subdivisions as noted on typical cross section, designated on the definitive plan and otherwise determined and approved by the Planning Board. Prior to the commencement of the construction phase of development, a pre-construction conference shall be held between the Planning Board and/or its agent and the developer and/or his agent to be sure that all of the requirements herein are understood and will be met.
B.
Unless otherwise specified, all the work and the materials used in the work to be done shall conform to the requirements of the Commonwealth of Massachusetts, Department of Transportation, Standard Specifications for Highway and Bridges, 1988 Edition, as amended, hereinafter referred to as the "Standard Specifications," and the special provisions included hereinafter. Appropriate illustrations are found in the Commonwealth of Massachusetts, Department of Transportation, 1977 Construction Standards, as amended.
C.
Supplementing the aforesaid standard specifications, certain specifications or special provisions shall apply particularly to the work to be done hereunder. References in the following specifications, unless otherwise stated, are to the aforesaid standard specifications, amendments or addenda. These specifications and special provisions shall take precedence and shall govern when they are stricter.
D.
To facilitate reference, each paragraph in these specifications is noted with the paragraph number of the particular section as contained in the Standard Specifications.
E. COMMONWEALTH DEPARTMENT ENGINEER
Wherever in the Standard Specifications or other contractual documents the following terms, or pronouns in place of them, are used, the intent and meaning shall be interpreted by substitution as follows:
Town of Lunenburg.
Lunenburg Department of Public Works.
The Planning Board of the Town of Lunenburg acting directly or through an authorized representative; such representative acting within the scope of the particular duties entrusted to him.
F.
The extent of work required shall be as shown upon approved plans, and in compliance with the standard cross section plans. Stakes shall be set which will indicate the exact amount of cut or fill.
(1)
Offset stakes shall be set under the direction of a registered land surveyor at fifty-foot intervals and at each sewerage and drainage structure and at each hydrant to indicate the location and the exact amount of cut, fill or grade.
(2)
Improvements to minimize adverse environmental impact, if required, shall be installed in accordance with all details as shown on the approved definitive plan, and all possible measures shall be taken during construction to minimize dust and erosion.
(3)
No earth shall be removed from the area shown on a definitive plan except in accordance with the approved plan.
G.
As each construction operation is completed, it shall be inspected and approved by the proper Town authority prior to starting working on the succeeding operation.