[Added 11-15-2022 by Ord. No. 2022-03]
A. If the municipality determines that any requirement under this chapter cannot be achieved for a particular regulated activity, the municipality may, after an evaluation of alternatives, approve measures other than those in this chapter, subject to §
338-11.1B and
C.
B. Waivers
or modifications of the requirements of this chapter may be approved
by the municipality if enforcement will exact undue hardship because
of peculiar conditions pertaining to the land in question, provided
that the modifications will not be contrary to the public interest
and that the purpose of the chapter is preserved. Cost or financial
burden shall not be considered a hardship. Modification may be considered
if an alternative standard or approach will provide equal or better
achievement of the purpose of the chapter. A request for modifications
shall be in writing and accompany the stormwater management site plan
submission. The request shall provide the facts on which the request
is based, the provision(s) of the chapter involved and the proposed
modification.
C. No waiver
or modification of any regulated stormwater activity involving earth
disturbance greater than or equal to one acre may be granted by the
municipality unless that action is approved in advance by the Department
of Environmental Protection (DEP) or the delegated County Conservation
District.
[Amended 11-15-2022 by Ord. No. 2022-03]
The green infrastructure and low-impact development practices
provided in the BMP Manual1 shall be utilized
for all regulated activities to the maximum extent practicable. Water
volume controls shall be implemented using the Design Storm Method
in Subsection A or the Simplified Method in Subsection B below. For
regulated activity areas equal to or less than one acre that do not
require hydrologic routing to design the stormwater facilities, this
chapter establishes no preference for either methodology; therefore,
the applicant may select either methodology on the basis of economic
considerations, the intrinsic limitations on applicability of the
analytical procedures associated with each methodology, and other
factors.
A. The Design Storm Method (CG-1 in the BMP Manual1) is applicable to any size of regulated activity. This method requires
detailed modeling based on site conditions.
(1) Do not increase the postdevelopment total runoff volume for all storms
equal to or less than the two-year twenty-four-hour duration precipitation.
(2) For modeling purposes:
(a)
Existing (predevelopment) nonforested pervious areas must be
considered meadow in good condition.
(b)
Twenty percent of existing impervious area, when present, shall
be considered meadow in good condition in the model for existing conditions.
B. The Simplified Method (CG-2 in the BMP Manual1) provided below is independent of site conditions and should be
used if the Design Storm Method is not followed. This method is not
applicable to regulated activities greater than one acre or for projects
that require hydrologic routing to design of stormwater storage facilities.
For new impervious surfaces:
(1) Stormwater facilities shall capture at least the first two inches
of runoff from all new impervious surfaces.
(2) At least the first one inch of runoff from new impervious surfaces
shall be permanently removed from the runoff flow, i.e., it shall
not be released into the surface waters of this commonwealth. Removal
options include reuse, evaporation, transpiration, and infiltration.
(3) Wherever possible, infiltration facilities should be designed to
accommodate infiltration of the entire permanently removed runoff;
however, in all cases, at least the first 0.5 inch of the permanently
removed runoff should be infiltrated.
(4) This method is exempt from the requirements of §
338-13, Rate controls.