The municipality may include all costs incurred in the review
fee charged to an applicant. The review fee may include, but not be
limited to, costs for the following:
A. Administrative/clerical processing.
B. Review of the SWM site plan.
For SWM site plans that involve subdivision and land development,
the applicant shall provide a financial guarantee to the municipality
for the timely installation and proper construction of all stormwater
management controls as required by the approved SWM site plan and
this chapter. The security shall be in the form of cash, certified
check or a letter of irrevocable credit naming the Township as beneficiary,
be for a term of 18 months, and be in an amount equal to 110% of the
actual cost of the improvements and facilities so dedicated in accordance
with the provisions of Sections 509, 510, and 511 of the Pennsylvania
Municipalities Planning Code.