[Ord. 314, 5/13/1986, Art. IV, § 1]
No street in the Township of Ferguson may be completely closed to traffic at any time. One lane of traffic must be able to pass at all times to direct traffic through the work area, and all established traffic patterns must be maintained at all times. If all other means of traffic control have been exhausted, the Township may permit a road to be completely closed temporarily.
[Ord. 314, 5/13/1986, Art. IV, § 2; as amended by Ord. 820, 12/8/2003]
For small area pave cuts, the utility or contractor shall be required to complete the temporary restoration within 48 consecutive hours of the initial cut during the normal working week excluding holidays and weekends. Extension time may be allowed upon appeal to the Director of Public Works, provided the contractor substantiates sufficient reasons for the extension required. Work on long cuts, those of 25 feet in length or longer, shall proceed in a continuous manner. Permits for long cuts or capital improvements will not be granted during the months of November through March, inclusive; except by written permission from the Director of Public Works. The utility or contractor shall coordinate planned cuts in the Township streets with the paving program of the Township. A construction schedule comprising planned cuts shall be submitted to the Township Engineer as they become available. The Township will provide a paving program for a one-year period to the public utilities prior to February 15. Changes in the public utilities' schedule of planned cuts shall require confirmation from the Township Engineer. Changes in the Township paving program shall be submitted to all utilities at the earliest possible date to permit the utilities to adjust their respective schedule.
[Ord. 314, 5/13/1986, Art. IV, § 3; as amended by Ord. 820, 12/8/2003]
All excavations shall be commenced and completed by the use of reasonable work force. In congested areas, the Township may limit work to other than normal daytime working hours. At the cessation of work adequate steel plates or wooden planking shall be placed over the excavation while it is not being worked to ensure full traffic flow. The maximum length of any opening in the street shall be 50 feet, unless otherwise permitted, in writing, by the Director of Public Works.
[Ord. 314, 5/13/1986, Art. IV, § 4]
1. 
In peak traffic area, all excavated material shall be removed daily at the cessation of work. All gutters and drainage devices shall be kept clean of all debris and excavated material. Fire hydrants adjacent to the work shall at all times be readily accessible to fire apparatus, and no materials or obstruction shall be placed within 15 feet of any hydrant.
2. 
All material which is excavated shall be considered waste material and shall be disposed of by the utility or contractor beyond the project limits. In no case shall waste material be left at the work site.
[Ord. 314, 5/13/1986, Art. IV, § 5; as amended by Ord. 820, 12/8/2003]
Power driven saws shall be used on all cuts. The cuts must be of sufficient depth to provide a smooth edge. Opening in brick or Belgian block based streets shall be of sufficient width to expose one-half row of undisturbed interlocking stone. No pavement busters, such as drop hammers, hoe rams and the like shall be used without the written permission of the Township Engineer.
[Ord. 314, 5/13/1986, Art. IV, § 6; as amended by Ord. 820, 12/8/2003]
If there is damage to another utility's underground facilities, it shall be the responsibility of the party doing the work to contact the Township Engineer, and all concerned pertinent utilities in order to request him to have a Township representative inspect the condition before any backfilling is begun.
[Ord. 314, 5/13/1986, Art. IV, § 7; as amended by Ord. 820, 12/8/2003]
The Township Engineer must be notified in advance of all backfilling. Backfilling will be done in such manner as to obtain compaction throughout the entire length of backfill. Type 2RC stone shall be used in all backfilling. The method of backfill shall be consistent with good engineering practice, i.e., the material shall be placed in layers not to exceed six inches properly tamped using a mechanical tamper or a mechanical vibrator up to the bottom elevation of the pavement structure. All backfill shall be compacted in accordance with PennDOT Specifications, Publication 408, § 206.3, as amended and superseded.
[Ord. 314, 5/13/1986, Art. IV, § 8]
The permittee is responsible for all costs and expenses of making and maintaining temporary and permanent restorations of disturbed areas. Temporary restoration consists of a minimum of two inches of bituminous material and is maintained in place until permanent restoration can be made.
[Ord. 314, 5/13/1986, Art. IV, § 9; as amended by Ord. 820, 12/8/2003]
1. 
Only public utilities or their contractors will be permitted to make permanent restoration of openings in pavements. The restored pavements shall be guaranteed from failure until two years after the date of acceptance. Permanent restoration must be completed no sooner than 30 days nor later than 60 days of the initial cut. Any cuts made in the months of November through March shall be permanently restored within 30 days after hot asphalt becomes available.
2. 
Existing base and surface must be exposed six inches on each side on any failures that may have developed.
3. 
Permanent restoration of flexible base pavements shall consist of six inches of 2A stone sub-base; five inches of bituminous concrete base course, and two inches of ID-2 wearing course (or match existing pavement depths if greater than five inches BCBC and two inches ID-2) rolled to conform with the existing road, and the edges sealed with AC-20. All openings, regardless of size, must be permanently restored in accordance with PennDOT Specifications, Publication 408, as amended and superseded.
4. 
Upon any failure of restoration being reported to a public utility, the pertinent public utility shall begin repairs within 24 hours after such notification. Upon failure of the public utility to repair the cut in a satisfactory manner, the Township shall have the option to complete the work or to contract to complete the work and to bill the public utility which shall be responsible for the cost of the same.
[Ord. 314, 5/13/1986, Art. IV, § 10]
The permanent restoration of special type pavements, such as concrete, brick, Belgian block, cobblestone gutters, or tiles, shall consist of relaying the original wearing course in accordance with the original installation specifications in such a manner as to prevent settlement or other deterioration.
[Ord. 314, 5/13/1986, Art. IV, § 11]
No linestone or monument in the Township of Ferguson may be removed, altered or buried at any time. When work in the right of way requires the temporary removal of a linestone or monument, it must be preserved at the site and reset at the direction of a registered surveyor. All costs incident thereto, including surveys, shall be charged to the public utility or contractor. All costs incidental to exposing and/or resetting a linestone or monument shall be charged to the utility or contractor.
[Ord. 314, 5/13/1986, Art. IV, § 12]
All test holes and boring in the right of way shall require a permit. Restoration of bore holes shall follow immediately after testing with the application of asphalt permanent restoration or other water resistant plugs. A penalty will be charged for each test hole found unplugged.
[Ord. 314, 5/13/1986, Art. IV, § 13]
The utility and/or its contractor must replace in kind all pavement markings damaged or removed by pave cuts and work incident thereto. All markings must be replaced within five days after permanent restoration. The Township may contract to have the necessary repairs made and bill the utility.
[Ord. 314, 5/13/1986, Art. IV, § 14]
Electronic traffic control devices and ancillary equipment damaged, removed because of pavement excavations or work incident thereto, must be replaced by the utility or its contractor, in kind, in whole or in part as required by the Director of Public Works or his agent. The Township may contract to have the necessary repairs made and bill the utility.
[Ord. 314, 5/13/1986, Art. IV, § 15]
The Director of Public Works or his designee may inspect all permitted work, and an inspection fee shall be charged.
[Ord. 314, 5/13/1986, Art. IV, § 16]
Upon notification from the Director of Public Works of a planned street resurfacing or reconstruction, all utilities will be required to test their lines and services and to schedule necessary capital improvements and service connections prior to resurfacing or reconstruction. Thereafter, cuts will be permitted in the new pavement only in an emergency. Pave cuts made in new pavement shall be subject to a penalty. Open cutting of all pavements on streets is prohibited unless a utility is connecting to a line that is under the pavement or unless subsurface conditions prevent boring with casing. Essential services for new building construction shall be permitted. Essential services should not include the additional of an alternate or secondary source of fuel, water, heat or other service. Pavement shall be considered new for a period of five years from the date of placement.
[Ord. 314, 5/13/1986, Art. IV, § 17]
This Part provides for the laying, renewing and repairing of all electrical, gas, water, sewer, steam, telephone, cable television, or other pipes or conduits, in any street, before the paving, repaving of the same, and for making the necessary house connections with said pipes, and also for the necessary house connections and branches with and leading into main or lateral sewers; providing, that in no case, except as a sanitary measure or which the Supervisors shall be the judge, shall the Supervisors require such house connections to be extended further from such sewers, or from such gas, water or other pipes or conduits, than the inner line of the curbstone of such street. The Supervisors may, after notice to all companies, corporations, persons, and owners affected, and in default of compliance therewith, cause said pipes to be laid, renewed or repaired and said connections made, and collect the cost of paving and repairing all pipes and pipe connections, from the companies, corporations, or persons owning or operating the said gas, water, and other pipes or conduits, with interest; and the cost of the sewer connections shall be a lien against the land for whose benefit such connections are made. A separate lien may be filed therefor, or such sewer connection cost may be included in any lien filed for the cost of such street improvement, and the lien and the proceedings thereon shall be as in the case of other municipal liens.
[Ord. 314, 5/13/1986, Art. III, § 18]
The Township Engineer shall have the final decision for the determination of lines and grades for street construction. This decision shall be based on good engineering practice and municipal standards.
[Ord. 314, 5/13/1986, Art. IV, § 19]
1. 
The following for pipes and conduits are assigned to the utilities operating under this Act:
A. 
Gas lines shall be a minimum of 30 inches below subgrade.
B. 
Water and sewer lines shall be a minimum of 48 inches below subgrade.
C. 
Electric lines and conduits shall be a minimum of 36 inches below subgrade.
D. 
Telecommunication lines and cable television lines and conduits shall be a minimum of 24 inches below subgrade, for main lines and a minimum of four inches for service lines.
[Ord. 314, 5/13/1986, Art. IV, § 20]
Aerial installations of electric power transmissions, telecommunications and cable television lines suspend from supporting poles having their base and/or support wires within the public right of way and interfering with a roadway construction, reconstruction or repair project shall be relocated upon written order from the Director of Public Works to a point specified therein. The Township may require the utility to place its aerial facilities underground where it is deemed necessary or desirable. Hereafter, aerial installations shall be placed subject to approval by the Township. The Township shall assign horizontal corridors on a case-by-case basis for all new construction. All gate boxes, shut-off valves and other regulating devices underground for individual customers for gas, water, sewer, steam, electric and telecommunications and cable television lines shall be located outside the right of way.
[Ord. 314, 5/13/1986, Art. IV, § 21]
The Township may participate in the actual costs less betterments of utility relocation when an existing utility right of way is owned by the utility and interferes with a municipal construction project.
[Ord. 314, 5/13/1986, Art. IV, § 22]
Upon receipt of a letter from the Township authorizing the start of physical work, the utility shall commence work within 30 days unless otherwise stated by the Township with reasonable cause shown in order to clear the construction area. The utility shall perform the relocation work in accordance with the construction plan approved by the Township. Utility relocation shall be accomplished by the utility to assure its completion prior to the commencement of roadway construction. Areas of utility relocation of work which cannot be accomplished prior to the start of construction but can be accomplished simultaneously without restricting the roadway project contractor, may be done concurrently with the contractor's operations when approved by the Township. It is acknowledged that field conditions occasionally necessitate revision of the utility relocation plan. It shall be the responsibility of the utility to report and justify such revisions, to correct any data on file with the Township. Minor modifications of the relocation plan may be brought to the attention of the project engineer and shall be noted in the daily inspection report.