[Ord. 146, 2/18/1992, § 400]
1. The developer/contractor shall be completely responsible for proper
construction methods and safety procedures to prevent physical harm
to employees, Township representatives, residents, site visitors or
property damage of same.
2. In performing work, the developer/contractor shall conform to the
current Department of Labor, OSHA regulations.
3. Presence of an authorized Township representative or inspector shall
not relieve the developer/contractor from proper safety procedures.
Inspectors are present only for the purpose of quality control and
verification of materials, not as safety consultants to the developer/contractor.
[Ord. 146, 2/18/1992, § 401; as amended by Ord.
167, 12/17/1996]
1. Blasting for excavation will be permitted only after 24 hours'
notice to the Township, which reserves the right to regulate the time
of blasting. Blasting/excavation of rock noted on drawings or unexpectedly
encountered shall be at the responsibility of the developer/contractor
at no expense to the Township.
2. The type, strength of explosives used and storage shall conform to
the following: PADEP Title 25, Chapters 210 and 211; (latest) warnings
and instructions as adopted by the Institute of Makers of Explosives,
established for prevention of accidents in the use of explosives;
the manufacturer's specifications; and "Regulations for the Storage,
Handling and Use of Explosives" of the Pennsylvania Department of
Labor and Industry.
3. Preblast surveys are required prior to the use of explosives within
any public street right-of-way. Copies of preblast surveys shall be
provided to the Township. The developer/contractor shall be responsible
for any property damage or physical injury caused by blasting or accidental
explosion. Handling of explosives and blasting operations shall be
done by a workman qualified for this work and so licensed.
4. All blasting shall be field monitored using seismographic-type equipment
and shall be performed under the supervision of a blaster licensed
to practice in the Commonwealth of Pennsylvania.
5. The developer/contractor is responsible to keep and submit an accurate
record of each blast to the Township. The record shall show the general
location of the blast, depth and number of drill holes, the kind and
quantity of explosives used, ground velocity and displacements and
other data required for a complete record.
6. Blasting will be permitted only after 24 hours' notice to the
Township and after securing all appropriate permits from affected
utilities. No blasting shall be done adjacent to existing lines or
structures which may be damaged through blasting operations; and under
no circumstances shall blasting be done on the site during, or for
a period of at least 48 hours after, the placement of concrete. Approval
must be received from respective authorities for blasting within 100
feet of existing utilities.
7. Rock excavation around water and gas mains shall be accomplished
by hand with jackhammers or other suitable equipment. Utmost care
shall be taken to avoid disturbance of mains. All utilities and special
structures shall be carefully protected from the affects of blasting,
and any damage by blasting shall be promptly repaired at the expense
of the developer/contractor. Written permission must be received from
the Township for blasting within 50 feet of newly laid sanitary sewer.
Blasting in the vicinity of any utility shall be accomplished in accordance
with 73 P.S. §§ 161 through 173, as amended.
8. All blasts shall be properly matted and securely covered with cable
or rope matts placed in accordance with governing regulations. Special
care shall be exercised in areas where high-tension power lines are
located.
9. Prior to blasting, sufficient warning shall be given to all persons
in the vicinity, and traffic shall be stopped at the proper distance
from the site and controlled by watchmen.
10. The developer/contractor shall use the utmost care in the use of
explosives necessary for the completion of the work and not endanger
life or property. All blasting operations shall be done by experienced
personnel who have proper certificates or licenses. The handling and
use of explosives shall be done strictly in accordance with the specifications
issued by the United States Bureau of Mines and with any federal or
state regulations now in effect or that might become effective in
the future and in compliance with local and state laws. Failure to
observe necessary precautions will be sufficient grounds for temporary
suspension of the work. All explosives shall be transported and stored
in a secure manner in accordance with local and state laws. All vehicles
and such storage places shall be clearly marked "Dangerous - Explosives"
and shall be in care of a competent watchman at all times. In no case
shall caps or other detonators be stored or transported with dynamite
or other explosives. The location of magazines, or the storage of
explosives and the separate storage of detonators, shall be subject
to approval from applicable state agencies.
[Ord. 146, 2/18/1992, § 402]
1. The contractor shall be responsible for the condition of all excavations
made by him. All slides and cave-ins shall be removed by the contractor
at whatever time and under whatever circumstances they may occur.
Shoring and bracing shall be the responsibility of the developer/contractor
and shall be provided as necessary to maintain safe working conditions
in conformance to applicable OSHA regulations.
2. The failure or refusal of the Township to require the use of bracing
or sheeting; or a better quality, grade, or section, or larger sizes
of steel or timber; or to require sheeting, bracing struts or shoring
to be left in place, shall not in any way or to any extent relieve
the developer/contractor of any responsibility concerning the condition
of the excavation nor impose any liability on the Township. Any delays
initiated or caused by action of the developer, contractor, Township
or utility owners (or respective agents and employees of same) resulting
in keeping an excavation open longer than would otherwise have been
necessary does not relieve the contractor from the necessity of properly
and adequately protecting the excavation from caving or slipping nor
from any of his obligations relating to injury of persons or property.
3. All work performed and materials used for sheeting, bracing and shoring
shall be in conformity with the requirements of the State Department
of Labor and Industry and other state and local laws and requirements
for protection of workmen, adjoining property and the work.
4. All plank used for sheeting and sheet piling and all timber used
for braces, shores, and stringers or wailing strips shall be sound,
straight-grained, yellow pine, Douglas fir or other material of equal
strength. All plank and timber shall be free from cracks, shakes,
and large or loose knows. Plank shall be tongue and groove or grooved
and spliced if so required. Steel sheeting, if used, shall be the
standard and generally accepted product of a recognized manufacturer.
All materials used in the work shall conform to the current regulations
of the Pennsylvania Department of Labor and Industry for excavations
and construction and shall be at least equal to the dimensions set
forth therein. Voids found behind sheeting shall be immediately filled
with granular material and compacted.
5. Material for sheet piling, sheeting, bracing and shoring shall be
furnished and driven or set in place by the contractor in accordance
with current regulations of the Pennsylvania Department of Labor and
Industry for excavations and construction, or wherever required by
the developer's project engineer to protect the workers and the
public or to maintain the maximum trench widths regardless of whether
the same is, or is not, considered necessary by the contractor.
6. All sheeting, sheet piling, braces and shores shall be driven or
put in place by men specially skilled in such work and shall be so
arranged that they may be withdrawn as the trenches are backfilled
without injury to or settlement of structures and pavements.
7. Where the maximum width of trench may be exceeded under these specifications
and where permitted under the regulations of the Pennsylvania Department
of Labor and Industry, the sides of the trench may be sloped in lieu
of providing sheeting and bracing. If the slope of the trench banks
is permitted, the slope shall begin at a point of 12 inches above
the top of the pipe. Sheeting shall be installed as required by the
Department of Labor and Industry regulations to support the vertical
part of the excavation.
8. Sheeting, sheet piling, bracing and shoring shall be withdrawn and
removed as the trenches are being backfilled except where, and to
such extent as, the developer's project engineer shall request
in writing that the same be left in place. Sheeting left in place
as permitted by the Township shall be cut off four feet below finished
grade.
9. In withdrawing sheeting and sheet piling, special care shall be taken
to ensure that all voids or holes left by the planks as they are withdrawn
are filled with satisfactory material and thoroughly rammed with thin
rammers provided especially for that purpose.
[Ord. 146, 2/18/1992, § 403]
1. General.
A. The developer/contractor shall furnish necessary traffic control
devices and appurtenances as may be required by the Township and/or
PennDOT.
B. Absolutely no Township roadways may be closed without written permission
from the Township.
C. Absolutely no state highways may be closed without written permit
from the Pennsylvania Department of Transportation.
D. Prior to the start of any construction activity on a state or Township
road, an approved traffic control plan must be received from the appropriate
governmental agency.
2. State Right-of-Way.
A. All traffic control shall be in conformance to the traffic control
plan and figures as approved by PennDOT.
B. Any deviation from approved traffic control plan or permit shall
require written approval from PennDOT.
C. All traffic control devices and signs shall conform to 67 Pa. Code,
Chapter 203, Work Zone Traffic Control, and PennDOT Publication 234,
Handbook of Approved Signs (latest edition), or as directed by PennDOT.
3. Township Right-of-Way.
A. Traffic control shall be in conformance to a traffic control plan
prepared by a registered engineer as approved by the Township.
B. Any deviation from the traffic control plan shall require written
approval from the Township.
C. All traffic control devices and signs shall conform to 67 Pa. Code,
Chapter 203, Work Zone Traffic Control, and PennDOT Publication 236,
Handbook of Approved Signs (latest edition), unless otherwise specified
by the Township.
D. When road closing is not permitted by the Township, the developer/contractor
shall maintain a safe and controlled traffic flow around the work
area.
E. The developer/contractor shall be responsible for all employee safety
and safety awareness when work is being performed within a Township
right-of-way. The developer/contractor shall be responsible for any
injuries, accidents or property damage that occurs as a result of
inadequate or improper traffic control.
F. At the end of the workday, all streets shall be left in such a condition
whereby they can be readily opened and safely traveled without resulting
in danger or damage to motor vehicles or property.
G. At all times, streets shall be kept clean and free of mud, sediment
and debris. Whenever mud is tracked onto public roadways, same shall
be immediately removed by shovel and brooming. Use of a backhoe to
scrape roadway surface is absolutely prohibited. When a mud film develops
on the surface, the street shall be immediately pressure-washed and
swept with power brooms. A street-cleaning machine shall be utilized
as required by the Township. Sediment-laden water generated by pressure-washing
must be collected and filtered in a manner satisfactory to the Bucks
County Conservation District prior to discharge into a storm sewer
or watercourse.
4. Road Closings.
A. Notification.
(1)
Emergency/public services, including but not limited to East
Rockhill Township administrative officers, police, fire, ambulance,
schools and public transportation, must be notified by the contractor/developer
at least 48 hours in advance of a road closing. Residents/businesses
along the road to be closed must be notified in writing at least one
week in advance of closing. A copy of written notification to residents/businesses
must be provided to the Township.
(2)
Notification shall provide scheduling for completion of the
work, detour information and any other information to minimize inconvenience
to residents and businesses.
(3)
When scheduling or detouring differs from information originally
provided, subsequent notification shall be sent to residents and businesses
and copied to the Township.
(4)
Notification for subsequent scheduling/detour revisions shall
be verbal to emergency/public services. All businesses and residents
shall be provided with written notification (hand delivered) prior
to implementation of revised detouring and scheduling.
B. A state highway may only be closed with written permit and an approved
detour plan from the Pennsylvania Department of Transportation.
C. Township roads may be closed only with permission of the Township. Roads may not be closed until a detour plan as prepared by a registered engineer is approved by the Township. The plan shall be prepared in a manner satisfactory to the Township in conformance to Subsection
3 of this section. When the detour route involves use of any state highway, written approval must also be received from the Pennsylvania Department of Transportation.