[Ord. 806, 6/11/1996,
§ 11702]
All streets, roads, alleys or driveways in the Borough of Aspinwall
shall be designed, constructed, replaced and/or repaired in accordance
with the Pennsylvania Department of Transportation (PennDOT) standards
and specifications as contained in the current editions of the "Guidelines
for Design of Local Roads and Streets" and Form 408 Specifications,
unless otherwise specified in the Aspinwall Borough Specifications.
[Ord. 806, 6/11/1996,
§ 11703]
The provisions of this Part shall apply to any new street, whether
or not to be dedicated to the Borough, and to the repair, replacement
or reconstruction of any public or private street, road, alley or
driveway.
[Ord. 806, 6/11/1996,
§ 11704]
The plans for any proposed street construction, repair or replacement,
if being undertaken by a party other than the Borough or under a contract
with the Borough, shall be submitted to the Borough Manager at least
30 days prior to the start of construction. No work shall begin until
the plans are approved by the Borough Engineer.
[Ord. 806, 6/11/1996,
§ 11705; as added by Ord. 995, 12/10/2003]
1. Any person, firm or corporation who violates a provision of this
Part, or who fails to comply therewith, or with any of the requirements
thereof, shall be, upon conviction thereof, sentenced to pay a fine
of not less than $100 nor more than $1,000 for each violation, plus
costs, and in default of payment of said fine and costs, to imprisonment
to the extent permitted by law for the punishment of summary offenses.
2. A separate offense shall arise for each day or portion thereof in
which a violation is found to exist or for each section of this Part
found to have been violated. All fines and penalties for the violation
of this Part shall be paid to the Borough Treasurer.
3. The Borough may also commence appropriate actions in equity or other
to prevent, restrain, correct, enjoin, or abate violations of this
Part.